Identification

UMIS Number BG-RRP-1.015-1083-C02
Project Name Building school STEM environment and high-tech equipped and connected classrooms.
Beneficiary 000086985 CYRIL AND METHODISM SCHOOL
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 09.09.2024
Start Date 09.09.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Североизточен (BG33), Варна (BG331), Провадия, с.Кривня

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).: „Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване.“;, Contracted Amount: 28 421.77 , Reported Amount: 46 558.53

Participating Organizations

Partners None
Contractors
  • Contractor: Gatev Systems, Contracted Amount*: 6 539.97 , Reported Amount**: 13 079.88
  • Contractor: INOVATSII I KONSULTIRANE, Contracted Amount*: 9 118.71 , Reported Amount**: 9 997.63
  • Contractor: "SHIMEL" EOOD, Contracted Amount*: 17 013.54 , Reported Amount**: 15 990.96
  • Contractor: PANDA Cooperative, Contracted Amount*: 3 438.25 , Reported Amount**: 6 876.50
  • Contractor: TRI SOFT, Contracted Amount*: 306.78 , Reported Amount**: 613.56
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 8.00 , Reached amount: 0.00

Financial Information

Total Project cost 28 705.99 EUR
Grant 28 705.99 EUR
Self amount 0.00 EUR
Total actual amounts paid 27 627.45 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN