| UMIS Number | BG-RRP-13.009-0077-C01 |
| Project Name | BG-RRP-13.009 "Installation of Photovoltaic Systems (PHS) in existing social services, activity delegated by the state and purchase of electric vehicles, including connected charging stations for the provision of social services", in "Center for Rehabilitation and Integration - Gorna Malina". |
| Beneficiary | 000776178 MUNICIPALITY OF GORNA MALINA |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 25.11.2025 |
| Start Date | 25.11.2025 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектното предложение има за цел да модернизира и оптимизира нуждите и автопарка на "Център за рехабилитация и интеграция - Горна Малина" с адрес: с. Горна Малина, ул. " Двадесет и шеста, №13 намиращ се в УПИ XXV, кв. 55. Чрез монтиране на "Фотоволтаична инсталация за производство на електрическа енергия от възобновяеми източници с обща инсталирана мощност 29,750kw “ и „Зарядна станция с капацитет от минимум 22kw за зареждане на електрически автомобил, предоставящ социални услуги делегирани от държавата в община Горна Малина“ за собствени нужди. Проектът цели да намали енергийната консумация на Центъра и да подобри качеството на предлаганите социални услуги. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Purchased electric vehicles and connected charging stations, each with a minimum power of 22 kW, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Number of social services with installed PV power plants with a capacity of 15 to 30 kW, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 107 979.99 EUR |
| Grant | 107 979.99 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 14 607.96 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка на нов лек електроавтомобил със зарядна станция, за социалните услуги в община Горна Малина,
Estimated Amount: 45 500.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN