| UMIS Number | BG-RRP-4.032-0271-C01 |
| Project Name | Construction of an energy storage facility for the "Photovoltaic facility for the production of electrical energy, located on the ground and roof of a building in a land property with identifier 15761.32.40 in the village of Golyam Izvor, Samuil municipality, Razgrad district |
| Beneficiary | 207800228 SPRING SOLAR |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 19.03.2025 |
| Start Date | 19.03.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Съоръжението за съхранение на ел.енергия към ФЕЦ с номинлна мощност от 600 kW, е предвиден в размер на 300kW и с общ капацитет от 614.4 kWh. Системата ще се състои от 6 отделни модула с мощност от 50kW и капацитет от 102,4 kWh |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.30 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 0.61 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 0.60 , Reached amount: 0.00 |
| Total Project cost | 212 186.14 EUR |
| Grant | 102 258.38 EUR |
| Self amount | 109 927.76 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: доставка на система за съхранение на ел.енергия ;
инсталиране и монтаж ;
пускане и настройка .,
Estimated Amount: 212 186.13
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN