Identification

UMIS Number BG-RRP-4.026-0065-C01
Project Name Вариант 1: Компонент 2: Закупуване на фотоволтаични системи до 10 kWp, включително системи за съхранение на електрическа енергия.
Beneficiary Dimitar
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 30.04.2025
Start Date 30.04.2025
End Date 19.12.2025
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Пловдив, гр.Пловдив

Description

Brief description
BG-RRP-4.026 „Национална схема за подпомагане на домакинствата в областта на енергията от възобновяеми източници“ Вариант 1: Компонент 2: Закупуване на фотоволтаични системи до 10 kWp, включително системи за съхранение на електрическа енергия.
Activities
  • Activity: • Доставка и монтаж на фотоволтаична система до 10 kWp, която може да включва система за съхранение на електрическа енергия, включително техническо въвеждане (пускане) в експлоатация фотоволтаичните системи – закупуване на арматура, кабели, конструкция за монтаж на съоръжението, инвертори и др.: • Доставка и монтаж на фотоволтаична система до 10 kWp, която може да включва система за съхранение на електрическа енергия, включително техническо въвеждане (пускане) в експлоатация фотоволтаичните системи., Contracted Amount: 7 669.38 , Reported Amount: 8 308.50

Participating Organizations

Partners None
Contractors
  • Contractor: SD Soldr, Contracted Amount*: 5 368.56 , Reported Amount**: 8 308.50
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

None

Financial Information

Total Project cost 8 308.51 EUR
Grant 5 368.58 EUR
Self amount 2 939.93 EUR
Total actual amounts paid 5 368.56 EUR
Percentage of EU co-financing 83.34 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и изграждане на фотоволтаична система от 9kW, която може да включва и системи за съхранение на ел.енергия за домакинствата съгласно Национална система за подпомагане на домакинствата на възобновяеми източници., Estimated Amount: 10 941.65

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN