Identification

UMIS Number BG-RRP-1.015-1623-C01
Project Name Building school STEM environment and high-tech equipped and connected classrooms.
Beneficiary 000558546 OU "SVETI SVETI KIRIL I METODIY"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 18.10.2024
Start Date 18.10.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северен централен (BG32), Силистра (BG325), Тутракан, гр.Тутракан
  • България, Северна и югоизточна България (BG3), Северен централен (BG32), Силистра (BG325), Тутракан, с.Нова Черна

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Концепцията за изграждане на училищна STEM среда BG-RRP-1.015 '"УЧИЛИЩНА СТЕМ СРЕДА": Дейността е детайлно описана в Концепцията за изграждане на училищна STEM среда подписана с електронен подпис от директора на училището и от директора на Националния STEM център, и прикачена в секция 12 от Формуляра за кандидатстване, Contracted Amount: 92 029.44 , Reported Amount: 120 037.61

Participating Organizations

Partners None
Contractors
  • Contractor: DANIS 75 LTD, Contracted Amount*: 21 904.05 , Reported Amount**: 21 584.70
  • Contractor: A1 Bulgaria EAD, Contracted Amount*: 70 322.05 , Reported Amount**: 98 452.91
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 24.00 , Reached amount: 0.00

Financial Information

Total Project cost 92 949.73 EUR
Grant 92 949.73 EUR
Self amount 0.00 EUR
Total actual amounts paid 92 672.11 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: "ДОСТАВКА, МОНТАЖ И ГАРАНЦИОННА ПОДДРЪЖКА НА ОБОРУДВАНЕ ЗА ИЗГРАЖДАНЕ НА STEM СРЕДА“- ОУ Св. Св. Кирил и Методий, с. Нова Черна, Estimated Amount: 35 261.14
  • Differentiated position 1: 05911-2024-0001
    Contractor: A1 Bulgaria EAD
    Contract total funded value: 42 190.17

Notes: