| UMIS Number | BG-RRP-4.032-0189-C02 |
| Project Name | "Construction of a local battery storage power station (BESS) with an installed capacity of 0,240 MW and a storage capacity of 0,480 MWh connected to a photovoltaic power plant with an installed capacity of 0,770 MW." |
| Beneficiary | 148136527 EKOINVEST ASETS |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 06.03.2025 |
| Start Date | 06.03.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Предложението за изпълнение на инвестиция предвижда изграждане на локално съоръжение за съхранение на електроенергия (ЛСС) с мощност 0,240 MW и капацитет 0,480 MWh. Съоръжението ще бъде свързано към съществуваща фотоволтаична инсталация с инсталирана AC мощност 0,770 MW на кандидата "ЕКОИНВЕСТ АСЕТС" АД, разположена на покривни площи върху сгради в ПИ с идентификатор 27125.23.39, с. Езерово, обл. Варна. С изграждането на системата за съхранение се цели максимализиране на употребата на електроенергия от изградения фотоволтаичен парк. Дейността е съобразена с изискванията на принципа за „ненанасяне на значителни вреди“ върху околната среда и ще допринесе за екологичния преход на страната. Енергийният обект за производство на електрическа енергия от слънчева енергия е присъединен към съответната електрическа мрежа и отговаря на приложимите изисквания относно влиянието върху околната среда. Проектът ще осигури изграждане на локално съоръжение за съхранение на електроенергия (ЛСС) като част от комбиниран проект за изграждане на нова мощност за производство на електрическа енергия от слънчева енергия и за ЛСС. Предвидените ЛСС, както и изградените мощности по отношение на компонента за производство на електрическа енергия, отговарят на изискването за "нова мощност". |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.24 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 0.48 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 0.77 , Reached amount: 0.00 |
| Total Project cost | 123 221.34 EUR |
| Grant | 61 610.67 EUR |
| Self amount | 61 610.67 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: „Доставка, монтаж, провеждане на 72-часови проби и пуск на Локална система за съхранение на енергията (ЛСС) с инсталирана мощност 0,3225 MW и капацитет на съхранение 0,645 MWh към фотоволтаична централа с инсталирана мощност 0,770 MW, разположена на покривни площи върху сгради с идентификатори 27125.23.39.5, 27125.23.39.6, 27125.23.39.9, находящи се в ПИ с идентификатор 27125.23.39 по КККР на с. Езерово, общ. Белослав, обл. Варна с GPS координати: 43°12'37.17'' N 27°46'59.28''E“ ,
Estimated Amount: 123 221.34
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN