| UMIS Number | BG-RRP-4.032-0043-C01 |
| Project Name | Installation of an electrical energy storage facility with an installed power of 0.2 MW and a capacity of 0.466 MWh to a Photovoltaic power plant with an installed power of 0.3996 MWp and a maximum inverter AC power of 0.4 MW in a real estate with identifier 32576.33.48, Regulated Real Estate I-048, m. 33, "Biy Bair" district, Izgrev village, Elhovo municipality, Yambol region |
| Beneficiary | 201588277 KIK ENERGY - 1 |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 19.03.2025 |
| Start Date | 19.03.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
В поземлен имот с идентификатор 32576.33.48 представляващ УПИ I-048, масив 33, местност „Бий баир“, землище с. Изгрев, община Елхово е предвидено да се изпълни комбиниран проект представляващ монтаж на Локално съоръжение за съхранение на електроческа енергия (ЛСС) към Фотоволтаична електроцентрала Предвиден е монтаж на ЛСС със следните характеристики: - Максимална АС мощност на ЛСС – P/AC = 0,2 МW - Капацитет на ЛСС – С = 0,466 МWh - Ниво на DC напрежение на батерията – V/DC = 832V - Ниво на AC напрежение на присъединяване към ГРТ - ФтЕЦ – V/AC = 400V, 3P+N+PE - Мощност равна на 50% от инсталираната мощност на производствения компонент на Фотоволтаичната електроцентрала; - Режим на работа на ЛСС – зареждане на най-малко 75% от електрическата енергия произведена от Фотоволтаичната електроцентрала на годишна база; - ЛСС имат гарантиран (полезен) капацитет за продължителност от най-малко 2 часа гарантирания капацитет на ЛСС = 0,466 МWh максимална мощност на заряд/разряд = 0,2 MW C-Rate = 2,33 h - Площ върху която ще се монтира ЛСС – 8,55 кв.м. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.20 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 0.47 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 0.40 , Reached amount: 0.40 |
| Total Project cost | 119 488.91 EUR |
| Grant | 59 744.45 EUR |
| Self amount | 59 744.46 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: изготвяне на Проектна документация за Поставяем обект,
Estimated Amount: 613.55
|
| Procedure 2 |
Subject to due process: Придобиване на ЛСС,
Estimated Amount: 112 484.21
|
| Procedure 3 |
Subject to due process: придобиване на Система и софтуер за мониторинг и контрол,
Estimated Amount: 1 278.23
|
| Procedure 4 |
Subject to due process: Свързване на ЛСС към съоръженията на обекта, който се изгражда по комбинирания проект.,
Estimated Amount: 2 454.20
|
| Procedure 5 |
Subject to due process: строително-монтажни работи (СМР),
Estimated Amount: 1 891.78
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN