| UMIS Number | BG-RRP-4.023-1143-C01 |
| Project Name | Introduction energy efficiency measures in residential building, "Asen Peykov" St. No. 17, bl. 36A |
| Beneficiary | 0006963270550 Metropolitan Municipality - "Izgrev" district |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 29.05.2025 |
| Start Date | 29.05.2025 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектът предвижда въвеждане на мерки за енергийна ефективност съобразно изготвеното енергийно обследване |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors |
|
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Energy-efficiency renovation of residential buildings, Measure Unit: Renovated gross floor area of residential buildings (m2), Base Value: 0.00 , Target amount: 4 596.83 , Reached amount: 0.00 |
| Indicator 2 | Reduced greenhouse emissions, Measure Unit: Tones CO2, Base Value: 0.00 , Target amount: 145.72 , Reached amount: 0.00 |
| Indicator 3 | Reduction of the annual consumption of primary energy kWh/year., Measure Unit: kWh/година, Base Value: 945 329.27 , Target amount: 289 462.46 , Reached amount: 0.00 |
| Indicator 4 | % in primary non-renewable energy consumption, Measure Unit: %, Base Value: 0.00 , Target amount: 69.38 , Reached amount: 0.00 |
| Indicator 5 | Number of renovated housing units, Measure Unit: Number, Base Value: 0.00 , Target amount: 63.00 , Reached amount: 0.00 |
| Total Project cost | 583 479.90 EUR |
| Grant | 583 479.90 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 186 769.25 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Изготвяне на инвестиционен проект и авторски надзор,
Estimated Amount: 48 923.02
|
| Procedure 2 |
Subject to due process: Изготвяне на независима експертна оценка, изготвена от сертифициран енергиен одитор,
Estimated Amount: 5 515.66
|
| Procedure 3 |
Subject to due process: Изпълнение на строително-монтажни работи,
Estimated Amount: 1 468 777.02
|
| Procedure 4 |
Subject to due process: Организация и управление и за информация и публичност,
Estimated Amount: 16 864.84
|
| Procedure 5 |
Subject to due process: Осъществяване на строителен надзор и изготвяне на доклад за оценка на съответствието,
Estimated Amount: 23 717.32
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN