| UMIS Number | BG-RRP-4.033-0020-C01 |
| Project Name | New capacities for the production of electricity from renewable sources and storage of electricity at "KREMAK ENERGY"LTD ( previous BOLKAN SOLAR ENERGY EOOD) |
| Beneficiary | 201351890 "KREMAK ENERGY"LTD |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 10.11.2025 |
| Start Date | 10.11.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Едно от най-големите предизвикателства пред компания ни е да изградим в местност "Тепята" землището на с. Сборище, община Твърдица комбиниран проект за нова инсталирана мощност за производство на електрическа енергия от слънчева енергия с номинална мощност 2797,65 kW и локални съоръжения за съхранение на енергия с номинална зарядна/разрядна мощност 1300 kW и да допринесем за екологичния преход на страната. С реализацията на проектно ни предложение се очаква да осигурим намаляване на годишните въглеродни емисии, увеличаване на дела на електрическата енергия от възобновяеми източници и интегриране на производствените мощности от възобновяеми източници в мрежата при гарантиране сигурността и стабилността на електроенергийната система. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and commissioned part of new renewable electricity generation capacity (in case applying for only part of the planned new renewable electricity generation capacity), Measure Unit: MW, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 2.79 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 2.61 , Reached amount: 0.00 |
| Indicator 4 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 1.30 , Reached amount: 0.00 |
| Total Project cost | 987 999.46 EUR |
| Grant | 493 999.73 EUR |
| Self amount | 493 999.73 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Изграждане и монтиране на ЛСС, като компонент от комбинирания проект за производство на електроенергия от възобновяеми източници,
Estimated Amount: 1 932 359.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN