Identification

UMIS Number BG-RRP-6.004-3433-C06
Project Name "Delivery of production storage equipment and installations for the production of energy from autonomous photovoltaic systems for own consumption"
Beneficiary 207425835 ANTON POPOV LTD
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 23.06.2025
Start Date 23.06.2025
End Date 31.03.2026
Status of Implementation of the Contract/Order of the Grant Contracted
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Монтана (BG312), Берковица, с.Мездрея

Description

Brief description
В ПИИ е предвидено да се закупи оборудване за съхранение на продукция с включена система за събиране, обработка и анализ на данни, както и доставка и монтаж на Автономна ФЕЦ за 23,94 kWp на покрива на изделието
Activities
  • Activity: Оборудване за съхранение на продукция. : Оборудване за съхранение на продукция ., Contracted Amount: 0.00 , Reported Amount: 0.00
  • Activity: Автономна ФЕЦ.: Автономна ФЕЦ., Contracted Amount: 74 463.52 , Reported Amount: 75 466.69

Participating Organizations

Partners None
Contractors
  • Contractor: BOTORN KLIMA EOOD, Contracted Amount*: 348 965.91 , Reported Amount**: 349 969.09
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Award of grant agreements for support under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00
Indicator 2 Installed additional operational renewable energy capacity in MW, Measure Unit: MW, Base Value: 0.00 , Target amount: 23.94 , Reached amount: 0.02
Indicator 3 Projects under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 348 965.91 EUR
Grant 174 482.96 EUR
Self amount 174 482.95 EUR
Total actual amounts paid 174 482.95 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN