Identification

UMIS Number BG-RRP-1.015-1989-C03
Project Name School STEM environment in Professional High School of Veterinary Medicine "Prof. Dr. G. Pavlov" Dobrich
Beneficiary 000846655 Professional High School of Veterinary Medicine "Prof. Dr. G. Pavlov" Dobrich
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 18.10.2024
Start Date 18.10.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Североизточен (BG33), Добрич (BG332), Добрич-град, гр.Добрич

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM център и ВОСКС в училище: Дейността е детайлно описана в Концепцията за изграждане на Училищна STEM среда ( Приложение II към Поканата), подписана с електронен подпис от директора на училището и прикачена в секция 12 от Формуляра за кандиедатстване., Contracted Amount: 92 023.01 , Reported Amount: 51 583.98

Participating Organizations

Partners None
Contractors
  • Contractor: PUCHKOV LTD, Contracted Amount*: 17 977.02 , Reported Amount**: 26 965.53
  • Contractor: ZAGO Ltd, Contracted Amount*: 16 412.31 , Reported Amount**: 24 618.45
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 60.00 , Reached amount: 0.00

Financial Information

Total Project cost 92 943.24 EUR
Grant 92 943.24 EUR
Self amount 0.00 EUR
Total actual amounts paid 34 675.89 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN