| UMIS Number | BG-RRP-1.015-1876-C02 |
| Project Name | STEM "Center for young researchers" and "Learning workshop (Maker Space)" Fields: "Robotics and Cyber-physical systems", Design and 3D Prototyping", "Natural Sciences" and "Mathematics and Informatics" The learning content that will be integrated is the content of Mathematics, Man and Nature, Geography and Economics, Technology and Entrepreneurship, Computer Modeling and IT, and Fine Arts. |
| Beneficiary | 000668252 30 SOU "BRATYA MILADINOVI" |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 20.09.2024 |
| Start Date | 20.09.2024 |
| End Date | 31.05.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС). |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 286.00 , Reached amount: 0.00 |
| Total Project cost | 258 202.41 EUR |
| Grant | 258 202.41 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 246 397.59 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: „Доставка, монтаж и въвеждане в експлоатация на технологично оборудване и обзавеждане за изграждане STEM
център в 30 СУ "Братя Миладинови" ", гр. София,
Estimated Amount: 259 385.21
|
| Procedure 2 |
Subject to due process: „Изпълнение на строително-монтажни работи за изграждане на STEM кабинети в 30. СУ „Братя Миладинови“ гр. София по проект BG-RRP-1.015 - "Училищна STEM среда“,
Estimated Amount: 142 164.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN