| UMIS Number | BG-RRP-1.011-0007-C01 |
| Project Name | "Repair and rehabilitation of the Center for support and personal development - student dormitory, Lovech" |
| Beneficiary | 000291591 MUNICIPALITY OF LOVECH |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 08.12.2023 |
| Start Date | 08.12.2023 |
| End Date | 31.05.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Сградата на ЦПЛР - Ученическо общежитие e разположена в Община Ловеч, гр. Ловеч, ж.к „Здравец“, бл.215. Построена е през 1980 година. Собственост е на Община Ловеч. Състоянието на сградата към момента не удовлетворява напълно изискванията на чл. 169 от ЗУТ по отношение съществените изисквания за безопасна експлоатация; опазване здравето и живота на хората; икономия на енергия и топлосъхранение. РЗП - 2 837,95 м2. Към момента в общежитието са настанени ученици от VIII-XII клас-89 бр., от които със статус на социално слаби - 12. Учениците се обучават в ППМГ, ПГИТУ, НПГВМ, СУ"Т.Кирков", ПГМЕТ. Капацитетът на общежитието е 183. ПИИ предвижда изпълнение на следните дейности: 1. Инженеринг - проектиране, авторски надзор и СМР по изпълнение на мерки за енергийна ефективност, които са предписани като задължителни за сградата в обследването за енергийна ефективност. Избран е Пакет №1 ЕСМ, с подробно описани дейности в Доклада за ЕО и Сертификата. Ще бъдат реализирани и СМР, които произтичат от нормативни изисквания, свързани с безопасната експлоатация на сградите и са предписани като задължителни в техническия паспорт на сградата. Предвижда се дейност оценка на съответствието на проектите, съгласно чл.142, ал. 4 и чл. 169 от ЗУТ и упражняване на строителен надзор по време на СМР. 2. Доставка и монтаж на оборудване и обзавеждане. 3. Организация и управление, вкл. информация, комуникация и публичност. За нуждите на ПИИ са изготвени Обследване за енергийна ефективност и сертификат за енергийни характеристики на сграда в експлоатация; Обследване за установяване на техническите характеристики, свързани с изискванията по чл. 169, ал. 1 (т. 1 - 5) и ал. 3 от ЗУТ и Технически паспорт на сградата; Очакваният брой потребители след изпълнението на ПИИ, които ще се възползват от услугата е 211, с планирани два от апартаментите на ет.1 да са за потребители в неравностойно положение - по 4 души в апартамент. Броят на персонала, който е ангажиран в предоставянето на услугата е 12. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Finalisation of renovation activities in student dormitories, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Savings in annual primary energy consumption, Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 363.06 , Reached amount: 0.00 |
| Indicator 3 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 211.00 , Reached amount: 0.00 |
| Total Project cost | 1 366 587.35 EUR |
| Grant | 1 366 587.35 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 770 585.61 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: „Осигуряване на мерки за информация, комуникация и публичност в изпълнение на инвестиции по Механизма за възстановяване и устойчивост, стълб „Иновативна България“, компонент 1 „Образование и умение, инвестиция 2 „Модернизация на образователната инфраструктура“ на Община Ловеч“,
Estimated Amount: 2 982.53
|
| Procedure 2 |
Subject to due process: „Осигуряване на мерки за информация, комуникация и публичност в изпълнение на инвестиции по Механизма за възстановяване и устойчивост, стълб „Иновативна България“, компонент 1 „Образование и умение, инвестиция 2 „Модернизация на образователната инфраструктура“ на Община Ловеч“ - запазена поръчка по смисъла на чл. 12, ал. 1, т. 1 от ЗОП“,
Estimated Amount: 0.00
|
| Procedure 3 |
Subject to due process: „Оценка на съответствието на инвестиционен проект и упражняване на строителен надзор съгласно чл. 168 от ЗУТ във връзка с изпълнението на обект „Ремонт и рехабилитация на Център за подкрепа и личностно развитие - ученическо общежитие, гр. Ловеч“,
Estimated Amount: 18 611.02
|
| Procedure 4 |
Subject to due process: Инженеринг - проектиране, извършване на строителни и монтажни работи и осъществяване на авторски надзор във връзка с изпълнението на обект „Ремонт и рехабилитация на Център за подкрепа и личностно развитие – ученическо общежитие, гр. Ловеч“,
Estimated Amount: 974 302.63
|
Notes: