| UMIS Number | BG-RRP-4.023-1942-C02 |
| Project Name | Energy renovation of a multi-family residential building of SS "KOMPLEKS BULGARKA", Tervel, ul. "Khan Asparuh No. 35, 35 A, 37, 39, 39 A" |
| Beneficiary | 000852925 Tervel munipality |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 14.05.2025 |
| Start Date | 14.05.2025 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Многофамилна жилищна сграда , в която има петдесет и четири самостоятелни обекта за жилищни нужди и шестнадесет обекта за нежилищни нужди (търговски обекти-11, гаражи-3, складово помещение-1 и зала-1 ) ще бъде енергийно обновена чрез изпълнение на пакет от енергоспестяващи мерки, предписани в доклад за енергийно обследване на сградата. Сградата представлява комплекс с четири входа , като под жилищната част има търговски обекти. Към сградата има и общи части - коридор пред апартаментите, стълбищна клетка и избени помещения в сутерена. Ще бъдат изпълнени: смяна на дограма, топлоизолация на фасади, топлоизолация на покрив, топлоизолация на под, подмяна на осветителни тела в общите части на сградата. Ще се изградят нови мълниезащита и заземителни системи.Инвестицията ще бъде изпълнена съгласно изготвен технически проект. За техническия проект ще бъде изготвен доклад за съответствието му със съществените изисквания към строежите и ще бъде издадено разрешение за строеж. По време на изпълнението на строителството ще се упражняват авторски и строителен надзор. След изпълнение на строителството, сградата ще бъде въведена в експлоатация. Ще се изготви независима експертна оценка от енергиен одитор, сертифициран по Закона за енергетиката . |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Energy-efficiency renovation of residential buildings, Measure Unit: Renovated gross floor area of residential buildings (m2), Base Value: 0.00 , Target amount: 5 410.74 , Reached amount: 0.00 |
| Indicator 2 | Reduced greenhouse emissions, Measure Unit: Tones CO2, Base Value: 0.00 , Target amount: 209.82 , Reached amount: 0.00 |
| Indicator 3 | Reduction of the annual consumption of primary energy kWh/year., Measure Unit: kWh/година, Base Value: 1 832 021.49 , Target amount: 832 385.23 , Reached amount: 0.00 |
| Indicator 4 | % in primary non-renewable energy consumption, Measure Unit: %, Base Value: 0.00 , Target amount: 54.56 , Reached amount: 0.00 |
| Indicator 5 | Number of renovated housing units, Measure Unit: Number, Base Value: 0.00 , Target amount: 54.00 , Reached amount: 0.00 |
| Total Project cost | 893 868.76 EUR |
| Grant | 883 506.08 EUR |
| Self amount | 10 362.68 EUR |
| Total actual amounts paid | 451 404.45 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Изготвяне на доклад за съответствие на технически проект и строителен надзор,
Estimated Amount: 23 266.18
|
| Procedure 2 |
Subject to due process: Изготвяне на технически проект и авторски надзор,
Estimated Amount: 47 993.26
|
| Procedure 3 |
Subject to due process: Изпълнение на строителни работи,
Estimated Amount: 1 344 479.15
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN