Identification

UMIS Number BG16RFOP002-6.002-0169-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 131156183 BG STEEL Ltd.
Funding ERDF ==> Innovations and Competitiveness
Date of the Contract/Order 16.09.2022
Start Date 16.09.2022
End Date 23.08.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Град (BG411), Столична, гр.София

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: „SIVEA” Ltd, Contracted Amount*: 12 575.00 , Reported Amount**: 25 150.00
  • Contractor: “DACH ENGINEERING” Ltd., Contracted Amount*: 113 534.80 , Reported Amount**: 227 069.60
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 252 219.60 BGN
Grant 126 109.80 BGN
Self amount 126 109.80 BGN
Total actual amounts paid 126 109.80 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: "Доставка и монтаж на Енергийно ефективни изолационни системи в сгради, конкретно многокомпонентни топлоизолационни системи за покриви - топлоизолационни плочи от минерална вата (2016 кв.м)", Estimated Amount: 232 941.00
  • Differentiated position 1: "Доставка и монтаж на Енергийно ефективни изолационни системи в сгради, конкретно многокомпонентни топлоизолационни системи за покриви - топлоизолационни плочи от минерална вата (2016 кв.м)"
    Contractor: “DACH ENGINEERING” Ltd.
    Contract total funded value: 113 534.80
Procedure 2 Subject to due process: "Доставка, монтаж и пускане в експлоатация на Компресор за сгъстен въздух, включително резервоар за сгъстен въздух, с инверторно управление (1 брой)", Estimated Amount: 35 717.00
  • Differentiated position 1: "Доставка, монтаж и пускане в експлоатация на Компресор за сгъстен въздух, включително резервоар за сгъстен въздух, с инверторно управление (1 брой)"
    Contractor: „SIVEA” Ltd
    Contract total funded value: 12 575.00

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN