Identification

UMIS Number BG-RRP-1.015-0213-C01
Project Name Construction of a school STEM environment in "P. Kr. Yavorov" elementary school, Ognyanovo
Beneficiary 000013097 OSNOVNO UCHILISHTE "P.K.YAVOROV"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 09.04.2024
Start Date 09.04.2024
End Date 09.04.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), Благоевград (BG413), Гърмен, с.Огняново

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM център и ВОСКС в училище: Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване., Contracted Amount: 179 996.15 , Reported Amount: 151 688.30

Participating Organizations

Partners None
Contractors
  • Contractor: MI BAU, Contracted Amount*: 67 451.44 , Reported Amount**: 84 314.30
  • Contractor: BALLISTIC CELL EOOD, Contracted Amount*: 112 290.00 , Reported Amount**: 67 374.00
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Брой, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: лица, Base Value: 0.00 , Target amount: 50.00 , Reached amount: 0.00

Financial Information

Total Project cost 181 796.11 BGN
Grant 181 796.11 BGN
Self amount 0.00 BGN
Total actual amounts paid 70 931.95 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: „Доставка, монтаж и въвеждане в експлоатация на оборудване за изграждане на STEM център в ОУ“П.Кр.Яворов“, с. Огняново“, Estimated Amount: 93 787.26
  • Differentiated position 1: „Доставка, монтаж и въвеждане в експлоатация на оборудване за изграждане на STEM център в ОУ“П.Кр.Яворов“, с. Огняново“
    Contractor: BALLISTIC CELL EOOD
    Contract total funded value: 112 290.00
Procedure 2 Subject to due process: Извършване на СМР дейности, Estimated Amount: 56 209.53

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN