UMIS Number | BG-RRP-4.020-0117-C01 |
Project Name | Building-construction activities for energy saving measures and energy renewal of the administrative building of Territorial Unit - Kardzhali of National Social Security Institute |
Beneficiary | 1210825210074 TP NA NOI - KARDZHALI |
Funding | RRF ==> Recovery and Resilience Plan |
Date of the Contract/Order | 20.05.2024 |
Start Date | 20.05.2024 |
End Date | 30.06.2026 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
Извършване на строително-ремонтни дейности за подобряване на енергийните характеристики на административната сграда на ТП на НОИ - Кърджали чрез топлинно изолиране на външните стени, еркери и покрив и подмяна на дограма. |
Activities |
|
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Намаляване на емисиите на парникови газове, Measure Unit: тонове CO2 екв., Base Value: 0.00 , Target amount: 34.05 , Reached amount: 0.00 |
Indicator 2 | Completed energy-efficiency renovation of non- residential buildings – renovated surface of public buildings (sub-measure 2), Measure Unit: m2, Base Value: 0.00 , Target amount: 1 070.34 , Reached amount: 0.00 |
Indicator 3 | Reduction of annual primary energy consumption, Measure Unit: kWh/година, Base Value: 0.00 , Target amount: 161 123.25 , Reached amount: 0.00 |
Indicator 4 | Completed energy renovation of non-residential buildings – number of renovated buildings (sub-measures 2 and 3), Measure Unit: Брой, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
Total Project cost | 363 829.79 BGN |
Grant | 320 864.46 BGN |
Self amount | 42 965.33 BGN |
Total actual amounts paid | 0.00 BGN |
Percentage of EU co-financing | 83.33 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: Проектиране и авторски надзор,
Estimated Amount: 15 975.00
|
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN