UMIS Number | BG16RFOP001-2.001-0099-C01 |
Project Name | Improvement of the energy efficiency of administrative buildings on the territory of the municipality of Samokov – the building of the municipality, the building of the regional police station, the building of „Avksenti Veleshki” school |
Beneficiary | 000776491 Municipality of Samokov |
Funding | ERDF ==> Regions in Growth |
Date of the Contract/Order | 02.11.2016 |
Start Date | 02.11.2016 |
End Date | 28.06.2019 |
Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
Location of Performance |
|
Brief description |
Описание на проектното предложение Сградите, предмет на проектното предложение са: 1. Обществена сграда: Административна сграда „Община Самоков”, състояща се от (1) Сграда на общинската администрация с РЗП 4 165 м2; (2) Ритуална зала с РЗП 670 м2; (3) Топла връзка и подземен гараж с РЗП 1 546 м2. 2. Сграда на ОУ „Митрополит Авксентий Велешки” в град Самоков с РЗП 4 047 м2. 3. Сграда на РПУ, гр. Самоков с РЗП 2 762 м2. Предвижда се изпълнение на мерки за енергийна ефективност, които са предписани като задължителни за сградата в обследването за енергийна ефективност. Основния ефект от изпълнението на мерките от проектното предложение на община Самоков е подобряване на енергийната ефективност на сградите, което пряко ще допринесе за намаляване на крайното потребление на енергия и косвено – за намаляване на емисиите на парникови газове. Допълнителният ефект се изразява в: осигуряване на рентабилна експлоатация на обществените сгради, което ще позволи устойчиво да продължи управлението и поддръжката им, с оглед предоставяне на по-добри и допълнителни услуги на населението и по този начин ще допринесат за намаляване на темпа на миграция към по-големите градове; запазване на традиционните функции на града, свързани с предлагане на обществени услуги не само за своето население, но също и за населението на околията; утвърждаване на добра практика на местно ниво, която да насърчи прилагането на подобни мерки, финансирани както от националния бюджет, така и от други източници. Конкретните цели са свързани с: повишаване на енергийната ефективност в обществените сгради, предмет на проектното предложение като се постигне най-малко клас на енергопотребление „С“ и се намалят разходите за енергия; подобряване на експлоатационните характеристики за удължаване на жизнения цикъл на сградите. |
Activities |
|
Partners |
|
Contractors |
|
Subcontractors |
|
Members of the Consortium |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Decrease of annual primary energy consumption of public buildings, Measure Unit: kWh/година, Base Value: 0.00 , Target amount: 3 106 885.00 , Reached amount: 3 294 683.00 |
Indicator 2 | Енергийна ефективност: Брой обновени сгради, Measure Unit: Number, Base Value: 0.00 , Target amount: 4.00 , Reached amount: 4.00 |
Indicator 3 | Estimated annual decrease of GHG, Measure Unit: тонове CO2 екв., Base Value: 0.00 , Target amount: 642.32 , Reached amount: 697.01 |
Total Project cost | 3 797 879.60 BGN |
Grant | 3 797 879.60 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 3 797 879.60 BGN |
Percentage of EU co-financing | 85.00 % |
|
|||||||||||||||||||||||||||||||||
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: Дейности по инженеринг /проектиране, СМР и авторски надзор/,
Estimated Amount: 3 179 646.90
|
Procedure 2 |
Subject to due process: Екип по проекта,
Estimated Amount: 0.00
|
Procedure 3 |
Subject to due process: Избор на изпълнител за информация и публичност,
Estimated Amount: 33 333.33
|
Procedure 4 |
Subject to due process: Избор на изпълнител на услугата :"Извършване на оценка за съответствие на инвестиционните проекти и упражняване на строителен надзор",
Estimated Amount: 102 500.00
|
Procedure 5 |
Subject to due process: Избор на изпълнител на услугата :"Извършване на оценка за съответствие на инвестиционните проекти и упражняване на строителен надзор",
Estimated Amount: 193 583.33
|
Procedure 6 |
Subject to due process: Избор на независим финансов одит,
Estimated Amount: 33 333.33
|
Procedure 7 |
Subject to due process: изготвяне на обследване за енергийна ефективност на административни сгради в гр.Самоков,
Estimated Amount: 16 800.00
|
Procedure 8 |
Subject to due process: Изготвяне на обследване за установяване на Техническите характеристики свързани с чл.169, ал.1 и 3 от ЗУТ и съставяне на технически паспорти на публични сгради в гр.Самоков,
Estimated Amount: 43 527.00
|
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN