Identification

UMIS Number BG06RDNP001-5.003-0009-C02
Project Name Purchase and installation of equipment to improve the biosecurity of a goat farm in the village of Bogutevo, municipality. Chepelare, region Plovdiv
Beneficiary 204310703 Eko Milk 99 LTD
Funding EZFRSR ==> Rural Development Programme
Date of the Contract/Order 03.02.2022
Start Date 03.02.2022
End Date 03.02.2024
Status of Implementation of the Contract/Order of the Grant Terminated (termination date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Смолян (BG424), Чепеларе, с.Богутево

Description

Brief description
- Проектното предложение предижда доставка и монтаж на съоръжения за дезинфекция на персонал и превозни средства.
 - Заболяванията имат негативно влияние на пазара на мляко и месо. При намаляване популацията на животните се намалява предлаганото количество мляко и месо, а от там закономерно се повишава цената на продукцията и се намалява търсенето. 
- предвидените по проекта съоръжения за измиване и дезинфекция са съобразени с капацитета на фермата, броя на персонала, както и на влизащите и излизащи превозни средства. Те ще осигурят чисти хигиенни условия за живот във фермата, както и безопастни условия на труд.
Activities
  • Activity: Закупуване на оборудване за повишаване биосигурността на фермата: Закупуване на оборудване, съгласно сключен договор, Contracted Amount: 42 897.39 , Reported Amount: 0.00
  • Activity: Консултантска услуга: Получаване на консултантски услуги по изготвяне и изпълнение на проект, Contracted Amount: 2 144.87 , Reported Amount: 0.00

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

None

Financial Information

Total Project cost 0.00 EUR
Grant 0.00 EUR
Self amount 0.00 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 0.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN