| UMIS Number | BG06RDNP001-4.001-0308-C05 |
| Project Name | "Plant for processing of fruits and vegetables", locality "Eleysite" Village of Skutare, Municipality of Maritsa, District Plovdiv |
| Beneficiary | 131567793 STROBAILS LTD |
| Funding | EZFRSR ==> Rural Development Programme |
| Date of the Contract/Order | 27.11.2019 |
| Start Date | 27.11.2019 |
| End Date | 27.11.2022 |
| Status of Implementation of the Contract/Order of the Grant | Contracted |
| Location of Performance |
|
| Brief description |
Настоящото проектно предложение предвижда изграждане и пускане в експлоатация на предприятие за преработка и съхранение на плодове и зеленчуци, с. Скутаре, общ. Марица. Извършване на необходимите СМР по изграждане на производствено хале, административно-битова сграда и вертикална планировка. Доставка на машини и оборудване, а именно: - линия за преработка и замразяване на ягоди - линия за преработка и замразяване на кръгли плодове и зеленчуци – домати, праскови, нектарини и др. - замразвателен тунел - Изграждане на хладилни камери за съхранение на готовата продукция. Машините и съоръженията са подбрани с капацитет, който отговаря на нуждите на критични за прибирането на реколтата условия, за да не се допуснат загуби от презряване, бране в неподходяща зрялост, или други дефекти, което води до влошаване на качеството и до загуби от протичане на нежелани физиологични процеси. Подробна информация относно технологичните процеси е дадена в специално разработена за предприятието част Технологична, от инженер-технолог с необходимото образование и дългогодишен проектантски опит. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| None |
| Total Project cost | 1 953 633.68 EUR |
| Grant | 976 816.85 EUR |
| Self amount | 976 816.83 EUR |
| Total actual amounts paid | 196 177.56 EUR |
| Percentage of EU co-financing | 75.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка на технологично оборудване,
Estimated Amount: 0.00
|
| Procedure 2 |
Subject to due process: Изготвяне на бизнес план,
Estimated Amount: 0.00
|
| Procedure 3 |
Subject to due process: Изготвяне на проект по част Технологична за обект Предприятие за преработка на плодове и зеленчуци - с. Скутаре, общ. Марица,
Estimated Amount: 0.00
|
| Procedure 4 |
Subject to due process: Изготвяне на технически проекти,
Estimated Amount: 0.00
|
| Procedure 5 |
Subject to due process: изпълнение на СМР,
Estimated Amount: 0.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN