Identification

UMIS Number BG06RDNP001-7.017-0007-C02
Project Name "Rehabilitation of the street network in the municipality of Kaspichan"
Beneficiary 000931511 OBSHTINA KASPICHAN
Funding EZFRSR ==> Rural Development Programme
Date of the Contract/Order 08.01.2025
Start Date 08.01.2025
End Date 15.09.2025
Status of Implementation of the Contract/Order of the Grant Contracted
Location of Performance
  • България, Северна и югоизточна България (BG3), Североизточен (BG33), Шумен (BG333), Каспичан

Description

Brief description
Проектното предложение на община Каспичан за рехабилитация на уличната мрежа, включва конкретни дейности в 5 населени места, с обща дължина на уличната мрежа - 3078 м. и площ 21 114,60 м2. на стойност 1 761 891.43 лв., което средно аритметично представлява 83,44 лв./м2.
Рехабилитацията на уличната мрежа е разпределена по населени места, както следва:
- ул. „Москва“, ул. „Рила“ и ул. „Ал. Стамболийски“ град Каспичан;
- ул. „Бузлуджа“ село Марково;
- ул. „Хан Аспарух“ и ул. „Христо Ботев“ село Могила;
- ул. „Христо Ботев“ село Върбяне;
- ул. „Васил Левски“ град Плиска.
Activities
  • Activity: Рехабилитация на ул. „Москва“ в гр. Каспичан: Рехабилитацията на ул. "Москва" в гр. Каспичан от км 0+000 до км 0+513 включва следните видове работи - подготвителни работи, земни работи, асфалтови работи, пътни работи, пътна маркировка и сигнализация., Contracted Amount: 209 067.93 , Reported Amount: 200 195.38
  • Activity: Рехабилитацията на ул. "Рила" в гр. Каспичан.: Рехабилитацията на ул. "Рила" в гр. Каспичан от км 0+000 до км 0+103 включва следните видове работи - подготвителни работи, земни работи, асфалтови работи, пътни работи, пътна маркировка и сигнализация., Contracted Amount: 32 724.48 , Reported Amount: 0.00
  • Activity: Рехабилитацията на ул. "Александър Стамболийски" в гр. Каспичан.: Рехабилитацията на ул. "Александър Стамболийски" в гр. Каспичан от км 0+000 до км 0+170 включва следните видове работи - подготвителни работи, земни работи, асфалтови работи, пътни работи, пътна маркировка и сигнализация., Contracted Amount: 40 548.59 , Reported Amount: 0.00
  • Activity: Рехабилитацията на ул. "Бузлуджа" в с. Марково.: Рехабилитацията на ул. "Бузлуджа" в с. Марково от км 0+000 до км 0+462 включва следните видове работи - подготвителни работи, земни работи, асфалтови работи, пътни работи, пътна маркировка и сигнализация., Contracted Amount: 120 792.53 , Reported Amount: 117 560.52
  • Activity: Рехабилитация на ул. "Хан Аспарух" в с. Могила: Рехабилитацията на ул. "Хан Аспарух" в с. Могила от км 0+000 до км 0+435 включва следните видове работи - подготвителни работи, земни работи, асфалтови работи, пътни работи, пътна маркировка и сигнализация., Contracted Amount: 90 571.21 , Reported Amount: 88 644.82
  • Activity: Рехабилитацията на ул. "Христо Ботев" в с. Могила: Рехабилитацията на ул. "Христо Ботев" в с. Могила от км 0+000 до км 0+575 включва следните видове работи - подготвителни работи, земни работи, укрепване на част от трасето чрез габиони, асфалтови работи, пътни работи, пътна маркировка и сигнализация. , Contracted Amount: 191 838.64 , Reported Amount: 182 028.67
  • Activity: Рехабилитацията на ул. "Христо Ботев" в с. Върбяне: Рехабилитацията на ул. "Христо Ботев" в с. Върбяне от км 0+000 до км 0+405 включва следните видове работи - подготвителни работи, земни работи, асфалтови работи, пътни работи, пътна маркировка и сигнализация. , Contracted Amount: 81 088.34 , Reported Amount: 81 212.02
  • Activity: Рехабилитацията на ул. "Васил Левски" в гр. Плиска: Рехабилитацията на ул. "Васил Левски" в гр. Плиска от км 0+000 до км 0+640 включва следните видове работи - подготвителни работи, земни работи, асфалтови работи, пътни работи, пътна маркировка и сигнализация. , Contracted Amount: 134 209.08 , Reported Amount: 132 474.46
  • Activity: Консултантски услуги по управление и отчитане на проекта: Предоставяне на консултантски услуги през целия период на реализиране на инвестицията, във връзка с нейното изпълнение, управление и отчитане., Contracted Amount: 8 998.74 , Reported Amount: 8 121.87
  • Activity: Упражняване на строителен надзор при изпълнение на СМР: Упражняване на строителен надзор при изпълнение на СМР по проект "Рехабилитация на улична мрежа в община Каспичан", Contracted Amount: 15 221.16 , Reported Amount: 15 052.44
  • Activity: Упражняване на авторски надзор при изпълнението на строително-монтажните работи : Упражняване на авторски надзор при изпълнение на СМР по проект "Рехабилитация на улична мрежа в община Каспичан", Contracted Amount: 8 998.74 , Reported Amount: 3 067.75

Participating Organizations

Partners None
Contractors
  • Contractor: "Hydrostroy" AD, Contracted Amount*: 3 067.75 , Reported Amount**: 3 067.75
  • Contractor: "CONSULT-64" Ltd., Contracted Amount*: 15 052.44 , Reported Amount**: 15 052.44
  • Contractor: "Motorways - Black Sea" AD, Contracted Amount*: 802 954.26 , Reported Amount**: 802 115.87
  • Contractor: Project Consulting Group - PKG EOOD, Contracted Amount*: 3 067.75 , Reported Amount**: 3 067.75
  • Contractor: "MN PROJECT CONSULT" LLC, Contracted Amount*: 8 121.87 , Reported Amount**: 8 121.87
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

None

Financial Information

Total Project cost 877 306.13 EUR
Grant 872 188.36 EUR
Self amount 5 117.77 EUR
Total actual amounts paid 1 239 732.67 EUR
Percentage of EU co-financing 85.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: „Упражняване на строителен надзор по време на строителството на обект „Рехабилитация на улична мрежа в община Каспичан” по обособени позиции, Estimated Amount: 15 221.16
  • Differentiated position 1: Упражняване на строителен надзор по време на строителството на обекти „Рехабилитация на ул. „Москва“ в гр. Каспичан" и „Рехабилитация на ул. „Бузлуджа“ в село Марково"
    Contractor: "CONSULT-64" Ltd.
    Contract total funded value: 4 852.16
  • Differentiated position 2: Упражняване на строителен надзор по време на строителството на обекти „Рехабилитация на ул. “Хан Аспарух“ в с. Могила“ и „Рехабилитация на ул. “Христо Ботев“ в с. Могила“
    Contractor: "CONSULT-64" Ltd.
    Contract total funded value: 5 036.23
  • Differentiated position 3: Упражняване на строителен надзор по време на строителството на обекти „Рехабилитация на ул. “Христо Ботев“ в с. Върбяне“ и „Рехабилитация на ул. “Васил Левски“ в гр. Плиска“
    Contractor: "CONSULT-64" Ltd.
    Contract total funded value: 5 164.05
Procedure 2 Subject to due process: Избор на изпълнител за извършване на строително-монтажни работи по проект „Рехабилитация на улична мрежа в община Каспичан”, Estimated Amount: 945 882.82
  • Differentiated position 1: Обособена позиция № 1: „Рехабилитация на ул. „Москва“ в гр. Каспичан" и „Рехабилитация на ул. „Бузлуджа“ в село Марково"
    Contractor: "Motorways - Black Sea" AD
    Contract total funded value: 318 083.35
  • Differentiated position 2: Обособена позиция № 2: „Рехабилитация на ул. “Хан Аспарух“ в с. Могила“ и „Рехабилитация на ул. “Христо Ботев“ в с. Могила“
    Contractor: "Motorways - Black Sea" AD
    Contract total funded value: 270 673.49
  • Differentiated position 3: Обособена позиция № 3: „Рехабилитация на ул. “Христо Ботев“ в с. Върбяне“ и „Рехабилитация на ул. “Васил Левски“ в гр. Плиска“
    Contractor: "Motorways - Black Sea" AD
    Contract total funded value: 214 197.42
Procedure 3 Subject to due process: Избор на изпълнител за упражняване на авторски надзор при изпълнение на СМР , Estimated Amount: 8 998.74
  • Differentiated position 1: упражняване на авторски надзор при изпълнение на СМР
    Contractor: "Hydrostroy" AD
    Contract total funded value: 3 067.75
Procedure 4 Subject to due process: Консултантски услуги, свързани с управлението на проекта, Estimated Amount: 8 998.74
  • Differentiated position 1: "Консултантски услуги по управление и отчитане на проект „Рехабилитация на улична мрежа в община Каспичан“
    Contractor: "MN PROJECT CONSULT" LLC
    Contract total funded value: 8 121.87
Procedure 5 Subject to due process: Упражняване на строителен надзор при изпълнение на СМР по проекта, Estimated Amount: 15 221.16

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN