| UMIS Number | BG06RDNP001-7.001-0116-C05 |
| Project Name | "Rehabilitation and reconstruction of" Bratya Miladinovi-Sever "Str., Stage 1: From Sofroniy Vrachabski Street (km 1 + 930) to Konstantin Fotinov St. (km 2+ 931.86) |
| Beneficiary | 000471536 Parvomai Munisipality |
| Funding | EZFRSR ==> Rural Development Programme |
| Date of the Contract/Order | 11.11.2021 |
| Start Date | 11.11.2021 |
| End Date | 20.02.2024 |
| Status of Implementation of the Contract/Order of the Grant | Contracted |
| Location of Performance |
|
| Brief description |
Проектното предложение се отнася за рехабилитация и реконструкция на ул. „Братя Миладинови-Север. Улицата се намира в гр. Първомай. Участъка, предвиден за реконструкция е от от ул. Софроний Врачабски(км 1+930) до ул. Константин Фотинов(км 2+ 931.86). Приблизителната й дължина е 1000 м. с променлив габарит приблизително от 6,50 м. до 8 м. Не по цялата дължина на улицата има изградени тротоари и положени бордюри. Предвижда се рехабилитация на пътната настилка на улицата, също така и реконструкция на съществуващите тротоари и ситуиране на нови, съответстващи на класа на улицата, прилежащата застройка и регулационния план. Предвижда се и подмяна на съществуващи бордюри и полагане на нови на местата, където такива няма. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| None |
| Total Project cost | 542 725.50 EUR |
| Grant | 542 725.50 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 515 683.41 EUR |
| Percentage of EU co-financing | 85.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Избор на изпълнител на СМР,
Estimated Amount: 471 775.53
|
| Procedure 2 |
Subject to due process: Избор на изпълнител на строителен надзор,
Estimated Amount: 0.00
|
| Procedure 3 |
Subject to due process: Подписване на договор за управление и отчитане на проекта,
Estimated Amount: 0.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN