Identification

UMIS Number BG06RDNP001-4.015-0352-C04
Project Name "Construction of a photovoltaic power plant and implementation of a comprehensive system for control and monitoring of production processes in a meat processing plant"
Beneficiary 200063974 DEKOVIS
Funding EZFRSR ==> Rural Development Programme
Date of the Contract/Order 12.10.2023
Start Date 12.10.2023
End Date 15.06.2025
Status of Implementation of the Contract/Order of the Grant Contracted
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), Благоевград (BG413), Благоевград, гр.Благоевград

Description

Brief description
Настоящият инвестиционен проект за “Изграждане на фотоволтаична централа и внедряване на цялостна система за контрол и проследяване на производствените процеси в месопреработвателно предприятие”  кандидатства за финансово подпомагане по Подмярка 4.2 „Инвестиции в преработка/маркетинг на селскостопански продукти” от Програмата за развитие на селските райони 2014-2020г. и съответства на основната цел на мярката - подобряване на цялостната дейност на предприятията от преработвателната промишленост, въвеждане на нови технологии, ВЕИ и софтуерни управление на  производството. 
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: EL KOMPLEKT 2004 LTD, Contracted Amount*: 33 898.65 , Reported Amount**: 67 838.20
  • Contractor: IV CONSULT 2015, Contracted Amount*: 1 695.96 , Reported Amount**: 4 090.33
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

None

Financial Information

Total Project cost 71 928.53 EUR
Grant 35 615.05 EUR
Self amount 36 313.48 EUR
Total actual amounts paid 35 615.06 EUR
Percentage of EU co-financing 88.76 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN