UMIS Number | BG16RFOP002-6.002-0912-C01 |
Project Name | Recovering SMEs by improving energy efficiency |
Beneficiary | 160052020 PLEXISTAB BULGARIA EAD |
Funding | ERDF ==> Innovations and Competitiveness |
Date of the Contract/Order | 21.09.2022 |
Start Date | 21.09.2022 |
End Date | 08.11.2023 |
Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
Location of Performance |
|
Brief description |
Възстановяване на МСП чрез подобряване на енергийната ефективност |
Activities | None |
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Number of enterprises receiving support, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
Indicator 2 | Number of enterprises receiving grants, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
Total Project cost | 133 088.15 BGN |
Grant | 66 544.07 BGN |
Self amount | 66 544.08 BGN |
Total actual amounts paid | 66 544.07 BGN |
Percentage of EU co-financing | 100.00 % |
|
|||||||||||||||||||||||||||||||||||||||
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: Доставка и монтаж на 11бр Wi-fi свързани трифазни електромери,
Estimated Amount: 18 975.00
|
Procedure 2 |
Subject to due process: Доставка и монтаж на охладител на въздух,
Estimated Amount: 35 000.00
|
Procedure 3 |
Subject to due process: Доставка и монтаж на чилър,
Estimated Amount: 77 740.00
|
Procedure 4 |
Subject to due process: Енергоспестяващи осветители 24W,
Estimated Amount: 5 000.00
|
Procedure 5 |
Subject to due process: Енергоспестяващи осветители 48W,
Estimated Amount: 8 000.00
|
Procedure 6 |
Subject to due process: Изработка и внедряване на Web базирана софруерна платформа,
Estimated Amount: 4 600.00
|
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN