Identification

UMIS Number BG06RDNP001-8.004-0010-C05
Project Name "Forest fire prevention activities in forests in the municipality of Stambolovo"
Beneficiary 000904261 Stambolovo Municipality
Funding EZFRSR ==> Rural Development Programme
Date of the Contract/Order 11.03.2021
Start Date 11.03.2021
End Date 15.09.2023
Status of Implementation of the Contract/Order of the Grant Contracted
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Стамболово
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Малък извор
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Жълти бряг
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Долно Ботево
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Лясковец
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Пътниково
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Силен
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Воденци
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Стамболово, с.Пчелари

Description

Brief description
Проектното предложение предвижда реконструкция и рехабилитация на горски пътища с обща дължина 9685,00 в горската територия на Община Стамболово, както и изграждане на един брой нов Резервоар за противопожарни нужди, изграждане на минерализовани ивици и лесокултурни прегради.
Activities
  • Activity: Строително ремонтни дейности : Изпълнението на СМР се извършва в съответствие със ЗУТ и започва след датата на подписване на Протокол за откриване на строителна площадка и определяне на строителна линия и ниво и осигурена възможност за започване на изпълнението., Contracted Amount: 2 671 527.36 , Reported Amount: 1 983 731.65
  • Activity: Авторски надзор: Извършване на Авторски надзор по време на изпълнение на СМР, Contracted Amount: 17 000.00 , Reported Amount: 40 995.41
  • Activity: Строителен надзор: Извършване на Строителен надзор по време на изпълнение на СМР, Contracted Amount: 25 400.00 , Reported Amount: 19 450.18
  • Activity: Консултантски услуги свързани с управление и отчитане на проекта: Извършване на Консултантски услуги по управление и отчитане на проекта по време на неговото изпълнение, Contracted Amount: 26 300.00 , Reported Amount: 20 448.94
  • Activity: Изграждане на нови минерализовани ивици и лесокултурни прегради: Изграждане на нови минерализовани ивици и лесокултурни прегради, Contracted Amount: 85 180.00 , Reported Amount: 79 853.50

Participating Organizations

Partners None
Contractors
  • Contractor: Transinjenerimg LTD, Contracted Amount*: 15 506.92 , Reported Amount**: 73 111.46
  • Contractor: Geodet LDT, Contracted Amount*: 22 314.06 , Reported Amount**: 19 450.18
  • Contractor: ATA - STROI LTD, Contracted Amount*: 2 461 542.18 , Reported Amount**: 2 063 585.15
  • Contractor: INTELLIIGENT CONSULTING LTD, Contracted Amount*: 22 827.29 , Reported Amount**: 41 412.68
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

None

Financial Information

Total Project cost 2 183 081.03 BGN
Grant 2 183 081.03 BGN
Self amount 0.00 BGN
Total actual amounts paid 2 162 011.62 BGN
Percentage of EU co-financing 85.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Строително ремонтни дейности , Estimated Amount: 2 037 000.00
  • Differentiated position 1: СМР по проект
    Contractor: ATA - STROI LTD
    Contract total funded value: 2 380 477.98
Procedure 2 Subject to due process: Изграждане на нови минерализовани ивици и лесокултурни прегради, Estimated Amount: 77 670.00
  • Differentiated position 1: Изграждане на нови минерализовани ивици и лесокултурни прегради
    Contractor: ATA - STROI LTD
    Contract total funded value: 81 064.20
Procedure 3 Subject to due process: Консултантски услуги свързани с управление и отчитане на проекта, Estimated Amount: 20 000.00
  • Differentiated position 1: Консултантски услуги свързани с управление и отчитане на проекта
    Contractor: INTELLIIGENT CONSULTING LTD
    Contract total funded value: 22 827.29
Procedure 4 Subject to due process: Строителен надзор, Estimated Amount: 20 370.00
  • Differentiated position 1: Строителен надзор
    Contractor: Geodet LDT
    Contract total funded value: 22 314.06

Notes: