Identification

UMIS Number BG-RRP-1.015-0304-C01
Project Name Creation of an integrated learning environment in the field of Natural and Mathematical Sciences.
Beneficiary 114550603 PGOT "HRISTO BOYADZHIEV"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 26.04.2024
Start Date 26.04.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Плевен (BG314), Плевен, гр.Плевен

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM център и ВОСКС в училище.: Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване.“;, Contracted Amount: 179 983.74 , Reported Amount: 133 942.27

Participating Organizations

Partners None
Contractors
  • Contractor: VESELIN BALEV EOOD, Contracted Amount*: 146 646.54 , Reported Amount**: 62 522.89
  • Contractor: VALEO INVEST, Contracted Amount*: 33 240.00 , Reported Amount**: 9 972.00
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 100.00 , Reached amount: 0.00

Financial Information

Total Project cost 181 783.57 BGN
Grant 181 783.57 BGN
Self amount 0.00 BGN
Total actual amounts paid 112 734.74 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: ДОСТАВКА И МОНТАЖ НА ТЕХНИЧЕСКО ОБОРУДВАНЕ ЗА ИЗГРАЖДАНЕ НА СТЕМ СРЕДА, Estimated Amount: 76 834.81
  • Differentiated position 1: ДОГОВОР
    Contractor: VESELIN BALEV EOOD
    Contract total funded value: 92 104.57

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN