UMIS Number | BG06RDNP001-7.001-0010-C03 |
Project Name | "Rehabilitation and reconstruction of streets in the town of Sevlievo" |
Beneficiary | 000215889 Municipality Sevlievo |
Funding | EZFRSR ==> Rural Development Programme |
Date of the Contract/Order | 14.06.2019 |
Start Date | 14.06.2019 |
End Date | 14.06.2022 |
Status of Implementation of the Contract/Order of the Grant | Contracted |
Location of Performance |
|
Brief description |
Проектното предложение предвижда реконструкция и рехабилитация на на улични и тротоарни настилки в град Севлиево на следните обекти: Улица "Цар Симеон" , Улица "Росица" гр.Севлиево и Улица "Стара Планина" гр.Севлиево |
Activities |
|
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
None |
Total Project cost | 1 100 496.48 BGN |
Grant | 1 100 496.48 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 1 100 496.48 BGN |
Percentage of EU co-financing | 85.00 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: Авторски надзор,
Estimated Amount: 10 582.84
|
Procedure 2 |
Subject to due process: Консултантски услуги за подготовка на заявление за кандидатстване,
Estimated Amount: 65 800.00
|
Procedure 3 |
Subject to due process: Консултантски услуги по управление и отчитане на проекта,
Estimated Amount: 10 582.84
|
Procedure 4 |
Subject to due process: Проектиране на улици в гр. Севлиево,
Estimated Amount: 20 000.00
|
Procedure 5 |
Subject to due process: СМР по проект "Рехабилитация и реконструкция на улици в град Севлиево",
Estimated Amount: 1 110 139.44
|
Procedure 6 |
Subject to due process: Строителен надзор,
Estimated Amount: 21 165.69
|
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN