UMIS Number | BG-RRP-1.015-1217-C02 |
Project Name | Izgrajdane na uchilishtna STEM sreda v Secondary school Neofit Rilski, town Harmanli |
Beneficiary | 000893256 SREDNO UCHILISHTE "NEOFIT RILSKI" |
Funding | RRF ==> Recovery and Resilience Plan |
Date of the Contract/Order | 26.09.2024 |
Start Date | 26.09.2024 |
End Date | 31.05.2026 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС). |
Activities |
|
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
Indicator 2 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 60.00 , Reached amount: 0.00 |
Total Project cost | 272 699.98 BGN |
Grant | 272 699.98 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 35 911.42 BGN |
Percentage of EU co-financing | 100.00 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: Изпълнение на строително-ремонтни работи за изграждане на „STEM център“ в Средно училище „Неофит Рилски“, гр. Харманли, по процедура за предоставяне на средства от Механизма за възстановяване и устойчивост BG-RRP-1.015 – „Училищна STEM среда“ по Национален план за възстановяване и устойчивост на Република България, финансирано от Европейския съюз – NextGenerationEU,
Estimated Amount: 50 360.00
|
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN