Identification

UMIS Number BG16RFOP002-6.002-0420-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 115876032 DGR INTERNATIONAL SRLU
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 22.11.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Сливен (BG342), Сливен, с.Гавраилово

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: "Sheiretov kampani" Ltd., Contracted Amount*: 46 156.87 , Reported Amount**: 92 313.74
  • Contractor: ET "ALANNI - Zyumbyulka Kostadinova" , Contracted Amount*: 23 176.86 , Reported Amount**: 46 353.72
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 138 667.48 EUR
Grant 69 333.74 EUR
Self amount 69 333.74 EUR
Total actual amounts paid 69 333.74 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Извършване на СМР, необходими за постигане на енергийна ефективност по проект BG16RFOP002-6.002-0420-C01, Estimated Amount: 139 451.79
  • Differentiated position 1: Обособена позиция № 1 - Енергийно ефективни изолационни системи в сгради - Топлоизолационни системи от сандвич панели за външни стени и подове към външен въздух с топлоизолация (PUR) полиуретан
    Contractor: "Sheiretov kampani" Ltd.
    Contract total funded value: 46 156.87
  • Differentiated position 2: Обособена позиция № 2 - Енергийно ефективни изолационни системи в сгради - Прозрачни ограждащи конструкции прозорци и врати с рамка от екструдиран поливинилхлорид (PVC)
    Contractor: ET "ALANNI - Zyumbyulka Kostadinova"
    Contract total funded value: 23 176.86

Notes: