UMIS Number | BG06RDNP001-6.012-1331-C02 |
Project Name | Procedure through selection of project proposals under sub-measure 6.3 "Starting aid for the development of small farms" from measure 6 of Gorcho Gorev |
Beneficiary | Gorcho |
Funding | EZFRSR ==> Rural Development Programme |
Date of the Contract/Order | 20.12.2022 |
Start Date | 20.12.2022 |
End Date | 20.12.2027 |
Status of Implementation of the Contract/Order of the Grant | Contracted |
Location of Performance |
|
Brief description |
В стопанството се отглежда лавандула, растежът ще бъде в същата посока , ще бъде внедрена иновативна станция за видеонаблядение . |
Activities |
|
Partners | None |
Contractors | None |
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
None |
Total Project cost | 29 337.00 BGN |
Grant | 29 337.00 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 29 337.00 BGN |
Percentage of EU co-financing | 100.00 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
There are no tender procedures |
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN