Identification

UMIS Number BG16RFOP002-6.002-0630-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 115891901 VAV 1991 Ltd
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 16.09.2022
Start Date 16.09.2022
End Date 18.07.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Пловдив, гр.Пловдив

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: AVA INGENERING 2018 LTD , Contracted Amount*: 62 888.90 , Reported Amount**: 125 777.80
  • Contractor: A2R INDUSTRIES LTD, Contracted Amount*: 6 391.15 , Reported Amount**: 12 782.30
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 138 560.10 EUR
Grant 69 280.05 EUR
Self amount 69 280.05 EUR
Total actual amounts paid 69 280.05 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на изсушител - 1 бр. , Estimated Amount: 5 112.92
  • Differentiated position 1: Доставка и монтаж на изсушител - 1 бр.
    Contractor: AVA INGENERING 2018 LTD
    Contract total funded value: 62 888.90
Procedure 2 Subject to due process: Доставка и монтаж на Камбани_Прожектори - 40 бр. - 150 вата., Estimated Amount: 12 782.30
  • Differentiated position 1: Доставка и монтаж на Камбани_Прожектори - 40 бр. - 150 вата.
    Contractor: A2R INDUSTRIES LTD
    Contract total funded value: 6 391.15
Procedure 3 Subject to due process: Доставка и монтаж на компресор - 1 бр. , Estimated Amount: 20 451.68
  • Differentiated position 1: Доставка и монтаж на компресор - 1 бр.
    Contractor: AVA INGENERING 2018 LTD
    Contract total funded value: 62 888.90
Procedure 4 Subject to due process: Доставка и монтаж на рекуператор - 3 бр. , Estimated Amount: 23 008.13
  • Differentiated position 1: Доставка и монтаж на рекуператор - 3 бр.
    Contractor: AVA INGENERING 2018 LTD
    Contract total funded value: 62 888.90
Procedure 5 Subject to due process: Доставка и монтаж на ресивър - 1 бр. , Estimated Amount: 6 135.50
  • Differentiated position 1: Доставка и монтаж на ресивър - 1 бр.
    Contractor: AVA INGENERING 2018 LTD
    Contract total funded value: 62 888.90
Procedure 6 Subject to due process: Доставка и монтаж на системи за хибридна вентилация - 3 бр. , Estimated Amount: 61 355.03
  • Differentiated position 1: Доставка и монтаж на системи за хибридна вентилация - 3 бр.
    Contractor: AVA INGENERING 2018 LTD
    Contract total funded value: 62 888.90
Procedure 7 Subject to due process: Доставка и монтаж на терпомомпи - 3 бр. , Estimated Amount: 9 714.55
  • Differentiated position 1: Доставка и монтаж на терпомомпи - 3 бр.
    Contractor: AVA INGENERING 2018 LTD
    Contract total funded value: 62 888.90

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN