Identification

UMIS Number BG16RFOP002-6.002-0773-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 200179391 BAMES
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 16.09.2022
Start Date 16.09.2022
End Date 23.08.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Кърджали (BG425), Черноочене, с.Черноочене

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: ET TOPLO- VALENTIN GOGEV, Contracted Amount*: 9 586.72 , Reported Amount**: 19 173.45
  • Contractor: BUS BAR ELEKTRO SISTEMI, Contracted Amount*: 5 276.53 , Reported Amount**: 10 553.06
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 29 726.50 EUR
Grant 14 863.25 EUR
Self amount 14 863.25 EUR
Total actual amounts paid 14 863.25 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на линейни осветители, Estimated Amount: 10 921.19
Procedure 2 Subject to due process: Доставка и монтаж на термопомпи въздух-въздух, Estimated Amount: 19 367.74

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN