UMIS Number | BG-RRP-1.007-0125-C01 |
Project Name | "RENEWAL OF THE INFRASTRUCTURE AND MEASURES TO INCREASE ENERGY EFFICIENCY, REPAIR AND DELIVERY OF EQUIPMENT AND FURNISHINGS OF THE BUILDING OF SU "CHRISTO SMIRNENSKI" - TOWN OF KOYNARE" |
Beneficiary | 000414154 RED BEACH MUNICIPALITY |
Funding | RRF ==> Recovery and Resilience Plan |
Date of the Contract/Order | 22.12.2023 |
Start Date | 22.12.2023 |
End Date | 31.05.2026 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
Проектното предложение предвижда извършване на строително монтажни работи за цялостен обновен облик на СУ "Христо Смирненски" - гр Койнаре“ и за постигане на енергийна ефективност в сградата; подобряване на достъпа на лицата с увреждания до и вътре в съответната сградана, както и доставка и монтаж на оборудване |
Activities |
|
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Savings in annual primary energy consumption, Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 278.86 , Reached amount: 0.00 |
Indicator 2 | Finalisation of renovation of schools and kindergartens, Measure Unit: Брой, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
Indicator 3 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: лица, Base Value: 0.00 , Target amount: 350.00 , Reached amount: 0.00 |
Total Project cost | 2 495 258.30 BGN |
Grant | 2 495 258.30 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 927 075.77 BGN |
Percentage of EU co-financing | 83.47 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: "ОБНОВЯВАНЕ НА ИНФРАСТРУКТУРАТА И МЕРКИ ЗА ПОВИШАВАНЕ НА ЕНЕРГИЙ-НАТА ЕФЕКТИВНОСТ, РЕМОНТ И ДОСТАВКА НА ОБОРУДВАНЕ И ОБЗАВЕЖДАНЕ НА СГРАДАТА НА СУ „ХРИСТО СМИРНЕНСКИ“ - ГР. КОЙНАРЕ",
Estimated Amount: 2 025 186.92
|
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN