| UMIS Number | BG16RFOP002-6.002-0196-C01 |
| Project Name | Recovering SMEs by improving energy efficiency |
| Beneficiary | 201965550 „GREYKO ENGINEERING“ LTD |
| Funding | ERDF ==> Innovations and Competitiveness 2014-2020 |
| Date of the Contract/Order | 16.09.2022 |
| Start Date | 16.09.2022 |
| End Date | 25.09.2023 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
Възстановяване на МСП чрез подобряване на енергийната ефективност |
| Activities | None |
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Indicator 2 | Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Total Project cost | 138 604.59 EUR |
| Grant | 69 302.29 EUR |
| Self amount | 69 302.30 EUR |
| Total actual amounts paid | 69 302.29 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: "Доставка, монтаж и пускане в експлоатация на енергийно-ефективни охладители на въздух",
Estimated Amount: 44 993.69
|
| Procedure 2 |
Subject to due process: "Доставка, монтаж и пускане в експлоатация на изсушител на сгъстен въздух",
Estimated Amount: 6 442.28
|
| Procedure 3 |
Subject to due process: "Доставка, монтаж и пускане в експлоатация на компресор за сгъстен въздух",
Estimated Amount: 18 406.51
|
| Procedure 4 |
Subject to due process: „Доставка и монтаж на енергийно-ефективни изолационни системи: 1) Многокомпонентна топлоизолационна система за външни (фасадни) стени; 2) Прозрачни ограждащи конструкции – прозорци“;,
Estimated Amount: 69 740.21
|
Notes: