Identification

UMIS Number BG16RFOP002-6.002-0291-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 130971270 V & T TRADE
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 25.10.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Област (BG412), Костинброд, с.Голяновци

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: NEW SYSTEM Ltd., Contracted Amount*: 17 240.76 , Reported Amount**: 34 481.52
  • Contractor: ENETRON LTD, Contracted Amount*: 35 279.14 , Reported Amount**: 70 558.28
  • Contractor: EMKO Ltd., Contracted Amount*: 15 972.76 , Reported Amount**: 31 945.52
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 136 985.32 EUR
Grant 68 492.66 EUR
Self amount 68 492.66 EUR
Total actual amounts paid 68 492.66 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Помпа - 4 бр., Estimated Amount: 32 415.91
  • Differentiated position 1: Помпа (4 бр.)
    Contractor: EMKO Ltd.
    Contract total funded value: 15 972.76
Procedure 2 Subject to due process: Система за енергиен мониторинг и енергиен мениджмънт, Estimated Amount: 35 023.49
  • Differentiated position 1: 1. Измерване на електрическа енергия в 43 точки;
    Contractor: NEW SYSTEM Ltd.
    Contract total funded value: 17 240.76
  • Differentiated position 2: 2. Софтуерна платформа - 1 бр.;
    Contractor: NEW SYSTEM Ltd.
    Contract total funded value: 17 240.76
Procedure 3 Subject to due process: Чилър с Агрегат с кондензатор за въздушно охлаждане (1 бр.), Estimated Amount: 72 028.24
  • Differentiated position 1: Чилър с Агрегат с кондензатор за въздушно охлаждане (1 бр.)
    Contractor:
    Contract total funded value:

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN