Identification

UMIS Number BG16RFOP002-2.073-16237-C01
Project Name Overcoming the shortage of funding and the lack of liquidity caused by the epidemic outbreak of COVID-19
Beneficiary 130882245 PROFIT AD
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 14.09.2020
Start Date 14.09.2020
End Date 29.04.2022
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Ямбол (BG343), Ямбол, гр.Ямбол

Description

Brief description
Преодоляване недостига на средства и липсата на ликвидност, настъпили в резултат от епидемичния взрив от COVID-19
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: RITAM-4-TB, Contracted Amount*: 0.00 , Reported Amount**: 653.92
  • Contractor: SPEED CONNECT, Contracted Amount*: 0.00 , Reported Amount**: 71.58
  • Contractor: VILTON, Contracted Amount*: 0.00 , Reported Amount**: 49.64
  • Contractor: DSG BULGARIA, Contracted Amount*: 0.00 , Reported Amount**: 1 493.63
  • Contractor: ADIKOM, Contracted Amount*: 0.00 , Reported Amount**: 238.47
  • Contractor: KUKOV, Contracted Amount*: 0.00 , Reported Amount**: 194.88
  • Contractor: Delfin, Contracted Amount*: 0.00 , Reported Amount**: 51.13
  • Contractor: VESELINA BIS, Contracted Amount*: 0.00 , Reported Amount**: 213.32
  • Contractor: WATER SUPPLY AND SEWERAGE LTD, Contracted Amount*: 0.00 , Reported Amount**: 529.38
  • Contractor: Elektrorazpredelenie Yug EAD, Contracted Amount*: 0.00 , Reported Amount**: 324.63
  • Contractor: Booking.com, Contracted Amount*: 0.00 , Reported Amount**: 323.65
  • Contractor: DIANJELI 1, Contracted Amount*: 0.00 , Reported Amount**: 152.36
  • Contractor: BOKSI-KONSTANTIN KOSTOV, Contracted Amount*: 0.00 , Reported Amount**: 174.16
  • Contractor: VEK - HOTELSKI KONSUMATIVI, Contracted Amount*: 0.00 , Reported Amount**: 642.18
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

None

Financial Information

Total Project cost 5 112.92 EUR
Grant 5 112.92 EUR
Self amount 0.00 EUR
Total actual amounts paid 5 112.92 EUR
Percentage of EU co-financing 85.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN