Identification

UMIS Number BG16RFOP002-6.002-0179-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 115599795 GLORIA - 2001
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 16.09.2022
Start Date 16.09.2022
End Date 27.01.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Пловдив, гр.Пловдив

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: BAER CONSULT LTD, Contracted Amount*: 33 175.68 , Reported Amount**: 66 351.36
  • Contractor: Meakomp Ltd., Contracted Amount*: 10 460.26 , Reported Amount**: 20 920.53
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 87 271.88 EUR
Grant 43 635.94 EUR
Self amount 43 635.94 EUR
Total actual amounts paid 43 635.94 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на 600 кв.м топлоизолация на външни стени с топлоизолационна плоча от EPS, Estimated Amount: 52 918.71
  • Differentiated position 1: Доставка и монтаж на 600 кв.м топлоизолация на външни стени с топлоизолационна плоча от EPS
    Contractor: BAER CONSULT LTD
    Contract total funded value: 26 459.35
Procedure 2 Subject to due process: Доставка и монтаж на дограма - 81,59 кв.м, с рамка от екструдиран поливинилхлорид (PVC), Estimated Amount: 13 432.65
  • Differentiated position 1: Доставка и монтаж на дограма - 81,59 кв.м, с рамка от екструдиран поливинилхлорид (PVC)
    Contractor: BAER CONSULT LTD
    Contract total funded value: 6 716.33
Procedure 3 Subject to due process: Доставка, монтаж и въвеждане в експлоатация на 1 бр. компресор с изсушител и 1бр. ресивър;, Estimated Amount: 20 920.53
  • Differentiated position 1: Доставка, монтаж и въвеждане в експлоатация на 1 бр. компресор с изсушител и 1бр. ресивър;
    Contractor: Meakomp Ltd.
    Contract total funded value: 10 460.26

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN