Identification

UMIS Number BG16RFOP002-6.002-0720-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 116552631 MT PLAST
Funding ERDF ==> Innovations and Competitiveness
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 20.03.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северен централен (BG32), Разград (BG324), Разград, гр.Разград

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: EUROMARKET COMPRESORS Plc, Contracted Amount*: 30 706.53 , Reported Amount**: 30 706.52
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 30 706.52 BGN
Grant 15 353.27 BGN
Self amount 15 353.25 BGN
Total actual amounts paid 15 353.27 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и въвеждане в експлоатация на Компресор за сгъстен въздух вкл. резервоар за сгъстен въздух с инвенторно управление с изсушител., Estimated Amount: 30 745.00

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN