Identification

UMIS Number BG16RFOP002-6.002-0474-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 115870168 MARIO LTD
Funding ERDF ==> Innovations and Competitiveness
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 25.10.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Марица, с.Войводиново

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: PEHIKS, Contracted Amount*: 0.00 , Reported Amount**: 8 900.00
  • Contractor: ASOLEK, Contracted Amount*: 0.00 , Reported Amount**: 5 379.84
  • Contractor: MARSI - PKM, Contracted Amount*: 0.00 , Reported Amount**: 17 672.00
  • Contractor: TECHNOMONTAJ EOOD, Contracted Amount*: 0.00 , Reported Amount**: 55 600.00
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 87 551.84 BGN
Grant 43 775.92 BGN
Self amount 43 775.92 BGN
Total actual amounts paid 43 775.92 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на енерго-ефективни изолационни сиситеми в производствената сграда - топлоизолационни системи от сандвич панели, прозрачни ограждащи конструкции прозорци и врати, секционни индустриални врати, Estimated Amount: 69 880.00
  • Differentiated position 1: Доставка и монтаж на енерго-ефективни изолационни сиситеми в производствената сграда - топлоизолационни системи от сандвич панели, прозрачни ограждащи конструкции прозорци и врати, секционни индустриални врати
    Contractor:
    Contract total funded value:
Procedure 2 Subject to due process: Закупуване на термопомпа за отопление и охлаждане, Estimated Amount: 17 672.00
  • Differentiated position 1: Закупуване на термопомпа за отопление и охлаждане
    Contractor:
    Contract total funded value:

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN