Identification

UMIS Number BG16RFOP002-6.002-0564-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 109599869 MICROTEL
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 01.09.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), Кюстендил (BG415), Кюстендил, гр.Кюстендил

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: MAVA INDUSTRIAL, Contracted Amount*: 12 929.34 , Reported Amount**: 10 774.46
  • Contractor: SMC Industrial Automation Bulgaria EOOD, Contracted Amount*: 1 044.90 , Reported Amount**: 870.75
  • Contractor: CONDEX, Contracted Amount*: 45 577.45 , Reported Amount**: 37 981.21
  • Contractor: DARSAS LTD, Contracted Amount*: 60 078.84 , Reported Amount**: 50 065.71
  • Contractor: "InnoLED" Ltd., Contracted Amount*: 2 061.53 , Reported Amount**: 1 717.94
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 101 410.06 EUR
Grant 50 705.02 EUR
Self amount 50 705.04 EUR
Total actual amounts paid 50 705.02 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Енергийно_ефективни_изолационни_системи_в_сгради, Estimated Amount: 6 391.15
  • Differentiated position 1: Доставка и монтаж на PVC дограма
    Contractor: DARSAS LTD
    Contract total funded value: 60 078.84
Procedure 2 Subject to due process: Енергийно_ефективни_изолационни_системи_в_сгради, Estimated Amount: 56 242.11
  • Differentiated position 1: Изграждане на топлоизолационна система на производствено хале на МИКРОТЕЛ ЕООД в гр. Кюстендил, ул. Оборище№4
    Contractor: DARSAS LTD
    Contract total funded value: 60 078.84
Procedure 3 Subject to due process: Енергоспестяващи_осветители, Estimated Amount: 3 313.17
  • Differentiated position 1: Доставка на линейни осветители
    Contractor: "InnoLED" Ltd.
    Contract total funded value: 2 061.53
Procedure 4 Subject to due process: Изсушители_на_сгъстен_въздух, Estimated Amount: 3 834.69
  • Differentiated position 1: Доставка на студен изсушител
    Contractor: SMC Industrial Automation Bulgaria EOOD
    Contract total funded value: 1 044.90
Procedure 5 Subject to due process: Компресори_за_сгъстен_въздух_вкл_резервоари_за_сгъстен_въздух, Estimated Amount: 13 804.88
  • Differentiated position 1: Доставка на винтов компресор
    Contractor: MAVA INDUSTRIAL
    Contract total funded value: 12 929.34
Procedure 6 Subject to due process: Рекуперативни_блокове_за_отопление_вентилация_и_охлаждане, Estimated Amount: 13 293.59
  • Differentiated position 1: Доставка на климатична техника
    Contractor: CONDEX
    Contract total funded value: 45 577.45
Procedure 7 Subject to due process: Термопомпи_за_отопление_и_охлаждане_вкл_за_загряване_на_вода_за_битови_нужди, Estimated Amount: 25 564.59
  • Differentiated position 1: Доставка на климатична техника
    Contractor: CONDEX
    Contract total funded value: 45 577.45

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN