Identification

UMIS Number BG16RFOP002-6.002-0743-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 126634781 ZKI VOLTA
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 16.09.2022
Start Date 16.09.2022
End Date 01.09.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Димитровград, гр.Димитровград

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: Elta - R Ltd., Contracted Amount*: 25 511.42 , Reported Amount**: 25 511.42
  • Contractor: Vi Vi Ai Grup LTD, Contracted Amount*: 11 785.28 , Reported Amount**: 11 785.28
  • Contractor: VIBO - T LTD, Contracted Amount*: 57 827.12 , Reported Amount**: 57 827.11
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 95 123.80 EUR
Grant 47 561.90 EUR
Self amount 47 561.90 EUR
Total actual amounts paid 47 561.90 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Енергийно ефективни изолационни системи в сгради - Многокомпонентни топлоизолационни системи за външни стени и подове към външен въздух топлоизолационна плоча от EPS, Estimated Amount: 12 347.70
  • Differentiated position 1: Енергийно ефективни изолационни системи в сгради - Многокомпонентни топлоизолационни системи за външни стени и подове към външен въздух топлоизолационна плоча от EPS
    Contractor: Vi Vi Ai Grup LTD
    Contract total funded value: 5 892.64
Procedure 2 Subject to due process: Енергийно ефективни изолационни системи в сгради - Прозрачни ограждащи конструкции прозорци и врати с рамка от алуминий с прекъснат топлинен мост, Estimated Amount: 58 429.31
  • Differentiated position 1: Енергийно ефективни изолационни системи в сгради - Прозрачни ограждащи конструкции прозорци и врати с рамка от алуминий с прекъснат топлинен мост
    Contractor: VIBO - T LTD
    Contract total funded value: 28 913.56
Procedure 3 Subject to due process: Енергоспестяващи осветители - Линейни осветители (31 ÷ 50; 51÷ 100) и Камбани прожектори (101 ÷ 150), Estimated Amount: 25 526.81
  • Differentiated position 1: Енергоспестяващи осветители - Линейни осветители (31 ÷ 50; 51÷ 100) и Камбани прожектори (101 ÷ 150
    Contractor: Elta - R Ltd.
    Contract total funded value: 12 755.71

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN