Identification

UMIS Number BG16RFOP002-6.002-0608-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 205970609 UMT AD
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 25.10.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Стара Загора (BG344), Казанлък, гр.Казанлък

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: KLIMAKOMPLEKT LtD., Contracted Amount*: 29 335.88 , Reported Amount**: 58 671.76
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 58 671.76 EUR
Grant 29 335.88 EUR
Self amount 29 335.88 EUR
Total actual amounts paid 29 335.88 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Закупуване, доставка и инсталация на оборудване за възстановяване на "ЮМТ" АД чрез подобряване на енергийната ефективност, Estimated Amount: 59 704.58

Notes: