Identification

UMIS Number BG16RFOP002-6.002-0122-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 203975618 MED INDUSTRY
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 23.08.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Плевен (BG314), Белене, гр.Белене

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: Himremontstroi Ltd, Contracted Amount*: 33 407.81 , Reported Amount**: 66 815.62
  • Contractor: Dulev amp; Dulev Ltd, Contracted Amount*: 40 062.32 , Reported Amount**: 80 124.64
  • Contractor: ZI EL TEHNILODGY Ltd, Contracted Amount*: 3 218.58 , Reported Amount**: 6 437.16
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 153 377.43 EUR
Grant 76 688.71 EUR
Self amount 76 688.72 EUR
Total actual amounts paid 76 688.71 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на енергийно ефективни осветителни тела, Estimated Amount: 6 442.28
  • Differentiated position 1: Доставка и монтаж на енергийно ефективни осветителни тела
    Contractor:
    Contract total funded value:
Procedure 2 Subject to due process: Подмяна на съществуващо единично метално остъкление с алуминиева дограма- стъклопакет, подмяна на стари метални врати и ремонт на покривно пространство на производствено хале, Estimated Amount: 146 940.27
  • Differentiated position 1: Подмяна на единично метално остъкление с алуминиева дограма- стъклопакет
    Contractor: Dulev amp; Dulev Ltd
    Contract total funded value: 40 062.32
  • Differentiated position 2: Подмяна на стари метални врати- 4 бр.
    Contractor: Dulev amp; Dulev Ltd
    Contract total funded value: 40 062.32
  • Differentiated position 3: Ремонт на покривно пространство на производствено хале
    Contractor: Himremontstroi Ltd
    Contract total funded value: 33 407.81

Notes: