Identification

UMIS Number BG16RFOP002-6.002-0677-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 122058078 NAK MASHY 97
Funding ERDF ==> Innovations and Competitiveness 2014-2020
Date of the Contract/Order 16.09.2022
Start Date 16.09.2022
End Date 21.07.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Област (BG412), Ботевград, гр.Ботевград

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: MASTER PLASTIK, Contracted Amount*: 15 543.27 , Reported Amount**: 31 086.55
  • Contractor: ENERGOINVEST 09, Contracted Amount*: 42 820.70 , Reported Amount**: 85 641.38
  • Contractor: Elma G - Stanislav Peev, Contracted Amount*: 7 183.65 , Reported Amount**: 13 114.64
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 129 186.84 EUR
Grant 64 593.41 EUR
Self amount 64 593.43 EUR
Total actual amounts paid 64 593.41 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

Reason % of financial
correction
Financial corrections amounts1,2 Contract
Grant Self-financing Total
Липса на добро финансово управление 5.00 327.87 327.86 655.73 ЕТ ЕЛМА - Г - СТАНИСЛАВ ПЕЕВ

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на енергоспестяваща осветителна система в производствена сграда , Estimated Amount: 13 114.64
  • Differentiated position 1: Доставка и монтаж на енергоспестяваща осветителна система в производствена сграда
    Contractor: Elma G - Stanislav Peev
    Contract total funded value: 7 183.65
Procedure 2 Subject to due process: Доставка и монтаж на Прозрачни ограждащи конструкции - външни прозорци, в производствена сграда, Estimated Amount: 48 040.99
  • Differentiated position 1: Доставка и монтаж на Прозрачни ограждащи конструкции - външни прозорци, в производствена сграда
    Contractor: MASTER PLASTIK
    Contract total funded value: 15 543.27
Procedure 3 Subject to due process: Топлоизолиране на външни стени към външен въздух на производствената сграда, Estimated Amount: 85 682.29
  • Differentiated position 1: Топлоизолиране на външни стени към външен въздух на производствената сграда
    Contractor: ENERGOINVEST 09
    Contract total funded value: 42 820.70

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN