Identification

UMIS Number BG16RFOP002-6.002-0126-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 160009243 HIDROYONIX
Funding ERDF ==> Innovations and Competitiveness
Date of the Contract/Order 16.09.2022
Start Date 16.09.2022
End Date 04.07.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Перущица, гр.Перущица

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: SOFTMAR, Contracted Amount*: 95 162.50 , Reported Amount**: 190 325.00
  • Contractor: TUV NORD Bulgaria EOOD, Contracted Amount*: 5 000.00 , Reported Amount**: 10 000.00
  • Contractor: Sirius Group C, Contracted Amount*: 4 000.00 , Reported Amount**: 8 000.00
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 208 325.00 BGN
Grant 104 162.50 BGN
Self amount 104 162.50 BGN
Total actual amounts paid 104 162.50 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Въвеждане и сертифициране на системи за енергиен мениджмънт в предприятията съгласно изискванията на стандарт БДС EN ISO 50001 (Energy Management Systems)/EN ISO 50001, Estimated Amount: 18 000.00
  • Differentiated position 1: Услуги по въвеждане на системи за енергиен мениджмънт в предприятията съгласно изискванията на стандарт БДС EN ISO 50001 (Energy Management Systems)/EN ISO 50001
    Contractor: Sirius Group C
    Contract total funded value: 4 000.00
  • Differentiated position 2: Услуги по сертифициране на системи за енергиен мениджмънт в предприятията съгласно изискванията на стандарт БДС EN ISO 50001 (Energy Management Systems)/EN ISO 50001
    Contractor: TUV NORD Bulgaria EOOD
    Contract total funded value: 5 000.00
Procedure 2 Subject to due process: Доставка на ДМА от предварително утвърден Списък на допустимите категории активи, Estimated Amount: 190 325.00
  • Differentiated position 1: Чилъри с топлинна мощност 69,50 kW - 2 броя;
    Contractor: SOFTMAR
    Contract total funded value: 95 162.50
  • Differentiated position 2: Рекуператори с максимален дебит 2000 m3/h - 3 броя;
    Contractor: SOFTMAR
    Contract total funded value: 95 162.50
  • Differentiated position 3: Компресор конвенционален с мощност 15 kW - 1 брой;
    Contractor: SOFTMAR
    Contract total funded value: 95 162.50
  • Differentiated position 4: Предварително изолирани тръби - 150 линейни метра;
    Contractor: SOFTMAR
    Contract total funded value: 95 162.50

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN