Identification

UMIS Number BG06RDNP001-7.007-0055-C01
Project Name "Construction of a sports ground and adjacent infrastructure on the territory of Strelcha, Strelcha Municipality"
Beneficiary 000351864 Strelcha Municipality
Funding EZFRSR ==> Rural Development Programme
Date of the Contract/Order 15.05.2019
Start Date 15.05.2019
End Date 15.05.2022
Status of Implementation of the Contract/Order of the Grant Contracted
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пазарджик (BG423), Стрелча

Description

Brief description
Проектът за изграждане на спортна площадка и прилежаща инфраструктура на територията на гр. Стрелча, община Стрелча, ще допринесе за обновяване на спортната инфраструктура в общината. Игрището е със стандартни размери, оградено с метална ограда и предвижда осветление.
Activities
  • Activity: „Изграждане на спортна площадка и прилежаща инфраструктура на територията на гр. Стрелча, община Стрелча”: По време на строителството ще бъдат изготвени всички изискуеми документи и актове съгласно ЗУТ., Contracted Amount: 90 759.50 , Reported Amount: 82 483.73
  • Activity: Строителен надзор : Дейността е свързана с осъществяване на независим строителен надзор при реализацията и изпълнението на обектите., Contracted Amount: 0.00 , Reported Amount: 1 000.00

Participating Organizations

Partners None
Contractors
  • Contractor: Zpoint Ltd., Contracted Amount*: 4 000.00 , Reported Amount**: 4 000.00
  • Contractor: POLIMIT KONSULT OOD, Contracted Amount*: 1 200.00 , Reported Amount**: 1 000.00
  • Contractor: ECO-HIDRO-90 OOD , Contracted Amount*: 96 308.76 , Reported Amount**: 76 878.47
  • Contractor: URISTA GROUP Ltd., Contracted Amount*: 1 605.16 , Reported Amount**: 1 605.26
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

None

Financial Information

Total Project cost 97 574.70 BGN
Grant 97 574.70 BGN
Self amount 0.00 BGN
Total actual amounts paid 83 324.85 BGN
Percentage of EU co-financing 85.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: „Изграждане на спортна площадка и прилежаща инфраструктура на територията на гр. Стрелча, община Стрелча”, Estimated Amount: 90 759.50
  • Differentiated position 1: „Изграждане на спортна площадка и прилежаща инфраструктура на територията на гр. Стрелча, община Стрелча”
    Contractor: ECO-HIDRO-90 OOD
    Contract total funded value: 96 308.76
Procedure 2 Subject to due process: Строителен надзор , Estimated Amount: 1 000.00
  • Differentiated position 1: Упражняване на стрроителен надзор
    Contractor: POLIMIT KONSULT OOD
    Contract total funded value: 1 200.00

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN