UMIS Number | BG06RDNP001-19.552-0007-C01 |
Project Name | "Delivery of a car for the needs of the Municipality of Ugarchin" according to a procedure through the selection of project proposals No. BG06RDNP001-19.552 LAG - Troyan, Apriltsi, Ugarchin M 7.2. "Investment in the creation, improvement or expansion of all types of small-scale infrastructure", |
Beneficiary | 000291716 Ugarchin Municipality |
Funding | EZFRSR ==> Rural Development Programme |
Date of the Contract/Order | 06.06.2024 |
Start Date | 06.06.2024 |
End Date | 30.06.2025 |
Status of Implementation of the Contract/Order of the Grant | Contracted |
Location of Performance |
|
Brief description |
Закупуване на нов автомобил за патронажни дейности на територията на община Угърчин. |
Activities |
|
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Население в територията, което се ползва от подобрените услуги, Measure Unit: Брой, Base Value: 0.00 , Target amount: 3 000.00 , Reached amount: 0.00 |
Indicator 2 | Проектите имат устойчиви резултати до 2025 г., Measure Unit: Брой, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
Indicator 3 | Брой проекти насочени към уязвими групи в територията, които се ползват от подобрените услуги, Measure Unit: Брой, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
Indicator 4 | Проектите са насочени към обекти, които са значими за местната общност, Measure Unit: Брой, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
Indicator 5 | Принос на проекта към целите и приоритетите на Стратегията, Measure Unit: Брой, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
Total Project cost | 48 037.00 BGN |
Grant | 48 037.00 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 0.00 BGN |
Percentage of EU co-financing | 90.00 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: „Доставка на лек автомобил за нуждите на Община Угърчин“ по процедура чрез подбор на проектни предложения № BG06RDNP001-19.552 МИГ – Троян, Априлци, Угърчин М 7.2. „Инвестиции в създаването, подобряването или разширяването на всички видове малка по мащаби инфраструктура“, приоритетна ос „Мярка 19 Водено от общностите местно развитие“, подмярка 19.2 „Прилагане на стратегии за Водено от общностите местно развитие“ от Програмата за развитие на селските райони за периода 2014-2020 г.",
Estimated Amount: 48 037.00
|
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN