Identification

UMIS Number BG-RRP-8.014-0004-C01
Project Name Implementation of the European Train Management System / ERTMS / on-board equipment of highway, zero-emission electric locomotives and zero-emission electric motor trains that operate on the conventional railway network of the Republic of Bulgaria.
Beneficiary 175403856 BDZ-Tovarni prevozi EOOD
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 01.12.2023
Start Date 01.12.2023
End Date 31.12.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България

Description

Brief description
Внедряване на Европейска система за управление на влаковете / ERTMS/ на бордовото оборудване на магистрални, нулево емисионни електрически локомотиви и нулево емисионни електрически мотрисни влакове, които оперират по конвенционалната ЖП мрежа на РБългария.
Предвижда се да се оборудват 19 броя локомотива със системата за за управление на влаковете / ERTMS/ .
Activities
  • Activity: „Проектиране, доставка и монтаж на бордово оборудване за ERTMS за част от подвижния състав на БДЖ ТП“: Сключване на партньорско споразумение за възлагане на поръчка с ДП Национална компания Железопътна инфраструктура. Подготовка на документация. Съгласуване на документацията за ОП /Обществената поръчка/. Комисия по ЗОП. Сключване ан договор., Contracted Amount: 20 946 702.00 , Reported Amount: 0.00

Participating Organizations

Partners
  • Partner: NATIONAL RAILWAY INFRASTRUCTURE COMPANY, Contracted Amount*: 0.00 , Reported Amount: 0.00
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Delivery and installation of the ERTMS/ETCS on-board equipment, Measure Unit: Брой, Base Value: 20 946 702.00 , Target amount: 20 946 702.00 , Reached amount: 0.00
Indicator 2 Delivery and installation of the ERTMS/ETCS on-board equipment, Measure Unit: Брой, Base Value: 20 946 702.00 , Target amount: 20 946 702.00 , Reached amount: 0.00

Financial Information

Total Project cost 20 946 702.00 BGN
Grant 10 473 351.00 BGN
Self amount 10 473 351.00 BGN
Total actual amounts paid 0.00 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN