UMIS Number | BG16RFOP001-3.002-0006-C01 |
Project Name | "Reconstruction (overhaul) of the Professional School of Energy and Electrical Galabovo, Building I, kv.83 - school building and training workshops" |
Beneficiary | 000817696 Galabovo Municipality |
Funding | ERDF ==> Regions in Growth |
Date of the Contract/Order | 05.12.2016 |
Start Date | 05.12.2016 |
End Date | 10.07.2018 |
Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
Location of Performance |
|
Brief description |
С проект "Реконструкция (основен ремонт) на Професионална гимназия по енергетика и електротехника гр.Гълъбово, УПИ I, кв.83 - учебна сграда и учебни работилници" се предвижда основен ремонт на учебната сграда с разгъната застроена площ 1936,38 кв. м. и прилежащи учебни работилници с разгъната застроена площ 2460,24 кв.м. или общо 4396,62 кв.м. Реализацията на основните проектни дейности, като ремонт на: - фасадите на сградите, вътрешните помещения - вкл.смяна на дограмата, строителните конструкции- покрив и др., електро мрежата, ВиК системите и ОВИК. Ще се изгради евакуационно стълбище, ще се осигури достъпна среда за ползване от хора с увреждания по изискванията на нормативните документи. Ще се извърши външно топлинно изолиране на стените на отопляемото пространство, изолация на покрива, цялостна подмяна на “сградната ВиК инсталация” и електрооборудването. Всички тези действия ще допринесат за изпълнение на основната цел на настоящата процедура BG16RFOP001-3.002 за създаване на условия за модерни образователни услуги, чрез подобряване на образователната инфраструктура в професионалните училища от национално и регионално значение. |
Activities |
|
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Representatives from marginalised groups, including roma benefiting from modernised eduicational infrastructure, Measure Unit: persons, Base Value: 0.00 , Target amount: 100.00 , Reached amount: 103.00 |
Indicator 2 | Брой на модернизираните образователни институции, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
Indicator 3 | Capacity of supported childcare or educational infrastructure, Measure Unit: persons, Base Value: 0.00 , Target amount: 423.00 , Reached amount: 423.00 |
Total Project cost | 1 405 999.20 BGN |
Grant | 1 399 999.20 BGN |
Self amount | 6 000.00 BGN |
Total actual amounts paid | 1 211 587.54 BGN |
Percentage of EU co-financing | 85.00 % |
|
|||||||||||||||
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: Въвеждане на обекта в експлоатация,
Estimated Amount: 1 000.00
|
Procedure 2 |
Subject to due process: Изпълнение на СМР,
Estimated Amount: 1 096 166.00
|
Procedure 3 |
Subject to due process: Информация и публичност,
Estimated Amount: 3 000.00
|
Procedure 4 |
Subject to due process: Одит на проекта,
Estimated Amount: 10 000.00
|
Procedure 5 |
Subject to due process: Организация и управление,
Estimated Amount: 5 000.00
|
Procedure 6 |
Subject to due process: Упражняване на авторски надзор на обекта,
Estimated Amount: 5 000.00
|
Procedure 7 |
Subject to due process: Упражняване на строителен надзор върху строително-монтажните работи ,
Estimated Amount: 20 000.00
|
Notes: