| UMIS Number | BG16RFOP001-2.001-0103-C03 |
| Project Name | Improvement of energy efficiency of buildings with identificators:65231.906.323, 65231.906.324,, 65231.906.325, 65231.905.138.1, 65231.906.483.1, 65231.906.483.2, 65231.904.54.1, 65231.909.312.1, 65231.911.299.1, 65231.905.135.1, 65231.908.28.1, 65231.906.212.1 |
| Beneficiary | 000776491 Municipality of Samokov |
| Funding | ERDF ==> Regions in Growth 2014-2020 |
| Date of the Contract/Order | 20.10.2016 |
| Start Date | 20.10.2016 |
| End Date | 20.07.2020 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
Проектът предвижда внедряване на мерки за енергийна ефективност в 11 сгради-3 блока и 8 жилищни сгради с цел подобряване на условията за живот. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors |
|
| Members of the Consortium |
|
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Estimated annual decrease of GHG, Measure Unit: тонове CO2 екв., Base Value: 0.00 , Target amount: 313.12 , Reached amount: 319.80 |
| Indicator 2 | Number of households with improved energy consumption classification, Measure Unit: домакинства, Base Value: 0.00 , Target amount: 84.00 , Reached amount: 86.00 |
| Indicator 3 | Енергийна ефективност: Брой обновени сгради, Measure Unit: Number, Base Value: 0.00 , Target amount: 11.00 , Reached amount: 11.00 |
| Total Project cost | 654 961.73 EUR |
| Grant | 654 961.73 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 654 961.72 EUR |
| Percentage of EU co-financing | 85.00 % |
|
|||||||||||||||||||||||||||||||||||||||
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|||||||||||||||||||||||||||||||||||||||
| Procedure 1 |
Subject to due process: екип за управление на проект,
Estimated Amount: 11 759.71
|
| Procedure 2 |
Subject to due process: Избор на изпълнител за инженеринг във връзка с изпълнението на проект „Подобряване на енергийната ефективност в сгради с идентификатори: 65231.906.323, 65231.906.324, 65231.906.325, 65231.905.138.1, 65231.906.483.1, 65231.906.483.2, 65231.904.54.1, 65231.909.312.1, 65231.911.299.1, 65231.905.135.1, 65231.908.28.1, 65231.906.212.1″,
Estimated Amount: 531 003.95
|
| Procedure 3 |
Subject to due process: Избор на изпълнител на информация и публичност,
Estimated Amount: 7 669.38
|
| Procedure 4 |
Subject to due process: избор на изпълнител на строителен надзор ОСИП,
Estimated Amount: 10 225.84
|
| Procedure 5 |
Subject to due process: Избор на фирма за независим финансов одит,
Estimated Amount: 3 834.69
|
| Procedure 6 |
Subject to due process: Изготвяне на обследвания за установяване на техническите характеристики , свързани с изискванията на чл.169, ал.1 и ал.3 от ЗУТ и съставяне на технически паспорт на съществуващи строежи и обследване за ЕЕ на 54 жилищни сгради на територията на община Самоков,
Estimated Amount: 0.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN